Machine Studies
Schedule for Run02-5, 2007
June 26th 0800 - June 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 6/26/07 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0820 |
Adjust RF2 TCU |
RF Group |
Stored Beam |
0820-1000 |
IOCMTIME work |
Laird |
No Beam |
0820-1000 |
Replace Maxwell PS for PAR kickers |
PS Group |
No Injection |
0820-1000 |
Replace Maxwell PS for SR kickers |
PS Group |
No Beam |
0820-0900 |
Inspect free-wheeling SCR boards B:Q |
PS Group |
No Injection |
0820-1000 |
Check pump 502 functionality |
Ferry |
No Beam |
0820-1000 |
CMPSI fiber output power measurements |
Pietryla |
No Beam |
1000-1200 |
CMPSI replacement |
Pietryla/PS group |
No Beam |
1000-1200 |
LCLS |
Pasky |
No injection |
1200-1400 |
S38 BPM work |
Erwin |
Stored beam & Inj. |
1400-2400 |
TBA |
|
|
|
Wednesday, 6/27/07 |
|
|
0000-0700 |
TBA |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |