Machine Studies
Draft Schedule for Run03-1, 2007
September 25 0800 – October 2 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, 9/24/07 |
|
|
1000-1300 |
First injection and preliminary orbit. recovery |
Emery Sajaev OPS |
Stored beam & injection |
1300-2400 |
RF conditioning. |
OPS |
Stored beam & injection |
|
Tuesday, 9/25/07 |
|
|
0000-1600 |
RF conditioning (continued). |
OPS |
Stored beam & injection |
1000-1200 |
Initial S35B:M pinhole camera setup. Parallel to RF conditioning. |
Yang |
Stored beam & injection |
1500-1800 |
CPU checkout. Part of it parallel to RF conditioning. |
Emery |
Stored beam & injection |
1800-2000 |
BM xbpm and rf bpm checkout. |
Hahne Erwin |
Stored beam & injection |
2000-2400 |
BPLD validation. |
Bui Brill |
Stored beam & injection |
|
Wednesday, 9/26/07 |
|
|
0000-0100 |
BPLD validation (continued). |
Bui Brill |
Stored beam & injection |
0100-0300 |
Collect RTFB data. |
Sun |
Stored beam & injection |
0300-0500 |
OPEN |
|
|
0500-0700 |
Investigate temperature sensor in S4B:V1 and back-flush S22:23 R1. |
Puttkammer |
NO BEAM |
0700-1100 |
ID xbpm checkout. |
Hahne |
Stored beam & injection |
1100-1900 |
Initial orbit recovery. Top-up 24 and 324 patterns. |
Decker Sajaev |
Stored beam & injection |
1900-2400 |
OPEN |
|
|
|
Thursday, 9/27/07 |
|
|
0000-0300 |
Reference lattice work. |
Emery Sajaev |
Stored beam & injection |
0300-0600 |
Setup corrector FF for datapool. |
Emery |
Stored beam & injection |
0600-1000 |
Linac PEM validation. |
Pasky |
No injection |
1000-1100 |
Verify orbit controllaw PV test. |
Shang |
Stored beam & injection |
1100-1500 |
P0 feedback study. |
Yao DiMonti |
Stored beam & injection |
1500-1900 |
Booster tune measurement test. |
Yao Gold Feng |
Stored beam & injection |
1900-2400 |
1ID, 2ID, and 23ID xbpm commissioning. |
Decker |
Stored beam & injection |
|
Friday, 9/28/07 |
|
|
0000-0300 |
1ID, 2ID, and 23ID xbpm commissioning (continued). |
Decker |
Stored beam & injection |
0300-0800 |
Beta function correction. |
Sajaev Xiao |
Stored beam & injection |
0800-1200 |
End to end shutter test. |
SI group |
No Beam |
1000-1100 |
Waveguide switch. Parallel to shutter test. |
RF group |
No Beam |
1200-1800 |
Multibunch instability study 1. |
Harkay |
Stored beam & injection |
1800-2200 |
Try new fill patterns. |
Emery Harkay |
Stored beam & injection |
2200-2400 |
CPU checkout. |
Emery |
Stored beam & injection |
|
Saturday, 9/29/07 |
|
|
0000-0100 |
CPU checkout (continued). |
Emery |
Stored beam & injection |
0100-0300 |
PEM testing with beam. |
OPS |
Stored beam & injection |
0300-1000 |
OPEN |
|
|
1000-1600 |
Multibunch instability study 2. |
Harkay Yang |
Stored beam & injection |
1600-2400 |
OPEN |
|
|
|
Sunday 9/30/07 |
|
|
0000-0600 |
Top-up operational readiness verification. |
OPS |
Stored beam & injection |
0600-0900 |
OPEN |
|
|
0900-1300 |
Test new FO beam loss detector at S9. |
Yao Dooling |
Stored beam & injection |
1300-1700 |
RTFB, datapool functional checkout. |
Decker |
Stored beam & injection |
1700-2400 |
OPEN |
|
|
|
Monday 10/01/07 |
|
|
0000-0300 |
OPEN |
|
|
0300-0600 |
Bunch purity monitor system setup. |
Yang |
Stored beam & injection |
0600-0800 |
Final S35B:M pinhole camera setup. |
Yang |
Stored beam & injection |
0800-1600 |
Final orbit, xbpm scripts testing. With 30 min. pause for waveguide switch around 1000. |
Decker Schroeder |
Stored beam & injection |
Around 1000 |
Waveguide switch. Exact time upon agreement with G. Decker. |
RF group |
NO BEAM |
1600-1900 |
Sextupole measurements with beam. |
Emery Sajaev |
Stored beam & injection |
1900-2200 |
Setup 16 mA single bunch. |
Emery Sajaev |
Stored beam & injection |
2200-2400 |
Optimize injection. |
Emery Sajaev |
Stored beam & injection |
|
Tuesday 10/02/07 |
|
|
0000-0200 |
Optimize injection (continued). |
Emery Sajaev |
Stored beam & injection |
0200-0600 |
Model measurement. |
Sajaev |
Stored beam & injection |
0600-0800 |
Prepare for user Operations (24 singlets, Top-Up, S32 RHB) |
OPS |
Stored Beam & Injection |