Machine Studies
Schedule for Run01-11, 2008
April 15th 0800 – April 16th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 4/15/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Document 12ID |
Wiemerslage |
Access Zone B |
0930-1030 |
10BM end to end test |
Forrestal |
No Beam |
0930-1000 |
Switch to back-up 352MHz RF source |
Bromberek |
No Beam |
0930-1130 |
Install Beam Position loss monitor |
Dooling/Gold |
Access Zone B |
0930-1130 |
23ID PS-1 work |
Banks |
Access Zone C |
1000-1100 |
Verify P0 feedback wiring in tunnel |
Yao |
Access Zone A |
1130-1230 |
Recovery from accesses |
Ops |
No beam |
1230-1400 |
Operator training |
Karl |
Limited Injection |
1230-1400 |
Shielding verification for 10-BMA (30ma for ½ hour, 50mA for ¾ hour) |
Ramanathan |
Stored beam & Occasional Inj. |
1400-1600 |
Test steering optimization PEM with positional steering at 14-ID |
Schroeder/ Shang/Graber |
Stored beam & injection |
1600-1900 |
P0 Feedback front end electronic test (24 singlets or single bunch |
Yao/Decker |
Stored beam & injection |
1900-2300 |
Lattice switch and orbit recovery for 324 singlets |
Decker/Emery |
Stored beam & injection |
2300-2400 |
CPU multipole center determination and Dipole correction |
Emery/Xiao |
Stored beam & injection |
|
Wednesday, 4/16/08 |
|
|
2400-0200 |
CPU multipole center determination and Dipole correction |
Emery/Xiao |
Stored beam & injection |
0200-0630 |
Test SPX lattice |
Sajaev |
Stored beam & injection |
0630-0800 |
Prepare for User beam (324 Non-top up) |
OPS |
Stored Beam & Injection |