Machine Studies
Draft Schedule for Run01-5, 2008
February 26th 0800 - February 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 2/26/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-0930 |
Reboot iocsrtune |
Stevens |
No Top up |
0900-930 |
Upgrade PAR bunch cleaning drive box |
Yao |
No Injection |
0900-1000 |
Multipactor studies (except L5) |
Cours |
No Injection |
0900-1000 |
L5 water skid repairs |
Wright |
No Injection |
0900-1100 |
Verify communication cables in SR |
PS group |
No beam |
0900-1100 |
Swap out Maxwell PS for SR:IK1 & B:IK |
Puttkammer |
No Beam |
0900-1200 |
Install cherenkov detectors |
Yang |
No Beam |
0930-1030 |
Replace linear encoder at 21ID |
Merritt |
Access Zone C |
0930-1030 |
Verify ventilation |
Jones, CF |
Access Booster |
0930-1130 |
Inspect/repair B4C9FL2 |
Gold |
Access Booster |
0930-1130 |
Inspect/repair B:IK |
Hillman |
Access Booster |
1100-1300 |
Check RF cavity tuning /check shielding |
RF group |
No Beam 1100-1200. Beam (but possible beam loss) 1200-1300 |
1200-1300 |
Check effect of removing bunch cleaning box on bunch purity |
Yao |
Stored beam |
1300-1400 |
Switch to Booster 132 nm lattice and check injection efficiency |
Sereno |
Stored beam & injection |
1400-1500 |
Switch PAR harmonic RF tube #2 and tune up beam to run for study period |
Yao |
Stored beam & occ. Inj. |
1500-1700 |
P0 feedback front-end checkout |
Yao |
Stored beam & occasional Inj. |
|
|
|
|
1500-1700 |
PEM testing |
Decker/Shang |
Stored beam & Occ. Inj. |
1700-2100 |
Orbit Recovery (24 bunch top-up, then 324 occ. Inj.) |
Decker/Sajaev/Emery |
Stored beam & Injction |
2100-2400 |
Continue RHB Setup |
Sajaev |
Stored beam & inj. |
|
Wednesday, 2/27/08 |
|
|
0000-0100 |
Continue RHB Setup |
Sajaev |
Stored beam & inj. |
0100-0400 |
CPU corrections AC&DC mode |
Emery/Xiao |
Stored beam |
0400-0600 |
Correlation of SR beam loss monitor signals with bunch injection efficiency |
Emery/Dooling |
Stored beam & inj. |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |