Draft Schedule for Run01-8, 2008
March 18th 0800 – March 19th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 3/18/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0830 |
Replace iocparbpm cpu |
Lenkszus |
Stored Beam & Injection |
0810-0930 |
Troubleshoot noisy S35:DCCT signal |
Brill/ |
Stored beam & occasional Inj. |
0900-0915 |
Reboot iocbvp2 |
DiMonte |
Limited Injection |
0930-1000 |
Set-up for 1+3*7 |
Sajaev |
Stored beam & injection |
1000-1600 |
1+3*7 top up mode user evaluation |
Ops/Users |
Stored Beam & Injection |
0900-1200 |
install a event receiver daughter board and event connection to the bunch cleaning system. |
Yao |
No impact |
0900-1300 |
Install new IRMIS PV crawler |
Quock |
No Impact (ioc and pv info not available) |
1300-1600 |
EQO RF rad surveys |
EQO/RF group |
Stored beam No Impact to Ops |
1600-1700 |
Re-install repaired Kalmus amplifier at RF4. |
RF group |
No Beam |
1600-1700 |
Check bunch cleaning readback problem |
Yao, Norum |
Limited Injection |
1700-1800 |
EQO RF rad surveys |
EQO/RF group |
No Beam (RF systems running) |
1800-2300 |
Test new SPX lattice |
Sajaev |
Stored beam & inj. |
2300-2400 |
New BTS Optics |
Emery/Sereno |
Stored beam & inj. |
|
Wednesday, 3/19/08 |
|
|
0000-0200 |
New BTS Optics |
Emery/Sereno |
Stored beam & inj. |
0200-0600 |
Check CPU coupling correction & CPU dipole corrections for new skew quad settings |
Emery |
Stored beam & injection |
0600-0700 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |