Machine Studies

Schedule for Run01-9, 2008

March 24th 0800 – March 26th 0800



Time

Descriptions

Studiers

SR Status


Monday, 3/24/08



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-0930

Switch from SRF-3 to SRF-2

RF group

No Beam

0900-0930

Reboot interleaving PS DSPs

Puttkammer

No Injection

0900-1000

Test Linac gun switch BESOCM test

Pasky, Hogrefe

No Injection

0900-1000

Reboot iocparawg

Norum

No impact

0900-1000

Install cable from S1 cabinet 3 to S2 P0 FB rack

Gold

No Impact

0900-1100

Replace PAR RF-1 meter relay

Grelick

No Injection

0900-1100

SR converter calibration tests

PS group

No Beam

0900-1300

NRTL inspections on SR Converters in Zone A

Puttkammer

No Beam

0930-1030

Troubleshoot RF4 klystron calorimetry

RF group

No Beam

0930-1030

Investigate RF5 sideband instability

RF group

No Beam

0930-1130

Repair Sector 11 Cherenkov detector

Yang

Access Zone B

1230-1400

SR training (setting up for injection, 1st half hour)

Schroeder/ Pasky

Stored beam & top-up

1300-1400

Investigage X-ray problem with RF2

RF Group

Stored beam& top-up

1400-1600

Test new positional steering optimization feature

Schroedr/ Graber

Stored beam & injection

1600-1800

Set-up RHB lattice

Emery/Sajaev

Stored beam & Injection

1800-2400

Orbit recovery (start with hybrid fill, then RHB 24 singlets)

Decker/Emery/ Sajaev

Stored beam & injection


Tuesday, 3/25/08



0000-0400

Continue SPX lattice

Sajaev

Stored beam & injection

0400-0600

PAR Operator training

Fystro

Limited injection

0600-0800

OPEN



0800-1100

Calibration of Cerenkov detectors (80-100mA no top up)

Yang

Stored beam

0800-1000

Install new epics software in iocparwg

Norum/Yao

No injection

1000-1100

Test new bunch cleaning application

Yao/Shang

No injection

1100-1300

Explore using tune measurement system to control blow up vertical size with minimized coupling and dispersion

Yao/Emery

Stored beam & injection

1300-1700

Test new booster long controllaw

Sereno

Occasional injection

1300-1700

Test new P0 Feedback front end electronics (24 singlets)

Yao/Decker

Stored beam

1700-2000

Real-time feedback studies

Decker/Sun

Stored beam & injection

1800-2000

PAR Operator training

Karl

Limited injection

2000-2400

Continue design quads

Sajaev

Stored beam & injection


Wednesday, 3/26/08



2400-0200

Continue design quads

Sajaev

Stored beam & injection

0200-0400

PAR operator training

Fystro

Limited injection

0400-0630

OPEN



0630-0800

Prepare for User beam

OPS

Stored Beam & Injection