Machine Studies

Schedule for Run02-2, 2008

June 17th 0800 - June 18th 0800



Time

Descriptions

Studiers

SR Status

 

Tuesday, 6/17/08

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-1000

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

1000-1030

Reboot interleaving DSPs

Puttkammer

No Injection

1000-1030

Reboot ioclibpm2

Pietryla

Limited Injection

1100-1200

Install guard over RF test stand emergency entrance enclosure

Hogrefe

No Beam

1000-1130

Troubleshoot rf2 power phase loop problem

Waldschmidt

No Beam

1130-1200

Switch from RF-2 to RF-3

Waldschmidt

No Beam

1000-1200

Replace Cherenkov boards S1, 3 & 5

Yang

No Beam

1000-1200

Linac reconfiguration.

Pasky Sereno

No injection

1200-1600

Monopulse BPM timing scans.

Decker Sajaev

Stored Beam & Injection

1600-2000

Xbpm studies.

Decker

Stored Beam & Injection

2000-2400

Measure HOM spectrum.

Harkay

Stored Beam & Injection

 

Wednesday, 6/18/08

 

 

0000-0300

Test PAR 300 MeV injection.

Yao Sereno

No injection

0300-0600

P0 feedback study.

Yao

Stored Beam & Injection

0600-0700

Investigate PAR timing problem.

Yao

No injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection