Machine Studies
Schedule for Run02-2, 2008
June 17th 0800 - June 18th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 6/17/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-1000 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
1000-1030 |
Reboot interleaving DSPs |
Puttkammer |
No Injection |
1000-1030 |
Reboot ioclibpm2 |
Pietryla |
Limited Injection |
1100-1200 |
Install guard over RF test stand emergency entrance enclosure |
Hogrefe |
No Beam |
1000-1130 |
Troubleshoot rf2 power phase loop problem |
Waldschmidt |
No Beam |
1130-1200 |
Switch from RF-2 to RF-3 |
Waldschmidt |
No Beam |
1000-1200 |
Replace Cherenkov boards S1, 3 & 5 |
Yang |
No Beam |
1000-1200 |
Linac reconfiguration. |
Pasky Sereno |
No injection |
1200-1600 |
Monopulse BPM timing scans. |
Decker Sajaev |
Stored Beam & Injection |
1600-2000 |
Xbpm studies. |
Decker |
Stored Beam & Injection |
2000-2400 |
Measure HOM spectrum. |
Harkay |
Stored Beam & Injection |
|
Wednesday, 6/18/08 |
|
|
0000-0300 |
Test PAR 300 MeV injection. |
Yao Sereno |
No injection |
0300-0600 |
P0 feedback study. |
Yao |
Stored Beam & Injection |
0600-0700 |
Investigate PAR timing problem. |
Yao |
No injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |