Schedule for Run02-3, 2008

June 24th 0800 - June 25th 0800



Time

Descriptions

Studiers

SR Status

 

Tuesday, 6/24/08

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1100

Replace / install Cherenkovs S1, 3, & 5

Yang

No Beam

0900-0930

Reboot ioclibpm2

Pietryla

Limited injection

0900-1000

Investigate stripline non-beam noise

Yao

Stored Beam & Injection

0900-1000

Switch from SRF-2 to RF-3

RF Group

No Beam

0900-1200

L5:TW:VP work

Grelick

No Beam

0900-1100

Install UPS outlets in D1128A

Gibson

Limited Injection

0900-1500

2 hrs PAR operator training

Karl

Limited Injection

1000-1200

Test RF5 AFG | Lower T-R cooling setpoints

Horan

No Beam

1200-1230

Inject 102 mA in 324 bunches.

OPS

Stored Beam & Injection

1230-1600

Continue 300MeV PAR/Booster injection.

Sereno

No injection

1230-1600

CPU AC mode correction (parallel to 300MeV injection).

Emery Xiao

Stored Beam

1600-1800

Study BPLD limits in vertical plane.

Emery

Stored Beam & Injection

1800-2200

Lifetime study.

Borland

Stored Beam & Injection

2200-2400

Monopulse BPM timing scan (or X-bpm studies).

Decker

Stored Beam & Injection

 

Wednesday, 6/25/08

 

 

0000-0200

Monopulse BPM timing scan (continued).

Decker

Stored Beam & Injection

0200-0600

P0 feedback test.

Yao

Stored Beam & Injection

0600-0700

Investigate PAR timing/phase.

Yao

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection