Machine Studies

Schedule for Run02-6, 2008

July 22nd 0800 – July 23rd 0800

Time

Descriptions

Studiers

SR Status

 

Tuesday, 7/22/08

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1100

RF levels at RF5 phase detectors

Horan

No Injection

 

Parasitic L5 conditioning

RF Group

Stored Beam & Injection

0900-1130

Replace Cerenkov detectors in S1-12

Brill

No Beam

0930-1130

Installation of LCLS BLM prototype

Yang

Access Zone B

1130-1200

Restore beam in the storage ring. Inject 324 bunches.

OPS

Stored Beam & Injection

1200-1500

12ID shutter thermal studies. Shutter permit required.

Capatina

Stored Beam & Injection

1200-1400

PAR/Booster training (parallel to 12ID shutter studies).

Fystro

Limited Injection

1500-1900

Xbpm alignment.

Decker

Stored Beam & Injection

1600-1800

PAR/Booster training (parallel to Xbpm alignment).

Karl

Limited injection

1900-2300

Measure bunch profile, etc.

Borland, Yang

Stored Beam & Injection

2300-2400

Setup hybrid fill pattern.

Sajaev

Stored Beam & Injection

 

Wednesday 7/23/08

 

 

0000-0300

Setup hybrid fill pattern (continued).

Sajaev

Stored Beam & Injection

0300-0700

P0 feedback.

Yao

Stored Beam & Injection

0700-0800

Prepare for user Operations

Ops

Stored Beam & Injection