Machine Studies
Schedule for Run02-7, 2008
July 28th 0800 – July 30th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, 7/28/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1000 |
RF waveguide switch |
Horan |
No Beam |
0900-1100 |
Replace RF loads at S36 |
RF group |
No Beam |
0900-1100 |
Replace Cherenkovs in S5-20 |
Yang |
No Beam |
0900-1100 |
Installation of UPS electrical outlets |
Gibson |
No Impact |
0900-1100 |
Check PAR bunch cleaning amp waveform |
Gold, Yao |
No Impact |
0930-1030 |
Install radiation paper on S40 cavities |
Bromberek |
Access Zone F |
1000-1400 |
Troubleshoot regulator boards for S:BM |
Puttkammer |
No Beam |
1200-1400 |
PAR/Booster training. Parallel to S:BM troubleshooting. |
Karl |
Limited Injection |
1400-1800 |
Setup hybrid. |
Sajaev |
Stored Beam & Injection |
1800-2200 |
Orbit recovery. |
Decker Sajaev |
Stored Beam & Injection |
2200-2400 |
BPM system checkout with hybrid. |
Decker |
Stored Beam & Injection |
|
Tuesday, 7/29/08 |
|
|
0000-0200 |
BPM system checkout with hybrid (continued). |
Decker |
Stored Beam & Injection |
0200-0600 |
P0 feedback study. |
Yao |
Stored Beam & Injection |
0600-1000 |
Retake CPU data. |
Xiao |
Stored Beam & Injection |
0800-1000 |
PAB/Booster training. Parallel to CPU study. |
Karl |
Limited injection |
1000-1400 |
12ID shutter thermal studies. |
Capatina |
Stored Beam & Injection |
1400-1600 |
Beam loss study. |
Dooling Harkay |
Stored Beam & Injection |
1600-1800 |
Setup All-ID-RHB for the next study. |
Sajaev |
Stored Beam & Injection |
1800-2400 |
Transverse instability study. |
Harkay Yang Sajaev |
Stored Beam & Injection |
|
Wednesday, 7/30/08 |
|
|
0000-0200 |
Setup 24 singlets with symmetric quads. |
Sajaev |
Stored Beam & Injection |
0200-0600 |
Reference lattice. |
Sajaev |
Stored Beam & Injection |
0600-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |