Machine Studies
Schedule for Run03-10, 2008
December 2nd 0800 – December 3rd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 12/2/08 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0900-0930 |
Reboot interleaving power supplies |
Fors |
No Injection |
0900-1000 |
Replace processor in iocs25fb |
Lenkszus |
No Beam |
0900-1000 |
Put scope on MPS switch input in S34 |
Smith, M. |
No impact |
0900-1000 |
Replace RF1 crowbar cabinet beacon |
Trento |
No impact |
0900-1300 |
nvestigate RF2's UVC control panel analog meter display issue |
Trento |
No Beam |
0900-1100 |
Diagnose & repair high flow readings for absorbers in S16, 19, 23 in SR absorber interlock chassis |
Putnam |
No beam |
0900-1000 |
Visual inspection of 352 Mhz trunk amplifier |
Horan |
No Beam |
0900-1100 |
Swap LTP:Q8 power supply |
Puttkammer |
No Injection |
0900-1100 |
Inspect B:BM and repair S12B:H4 |
Puttkammer |
No Injection |
0900-1300 |
Replace 200kw reject RF loads |
Horan |
No Beam |
0900-1300 |
Review existing interlock panel wiring at RF5 in order to complete PLC upgrade drawings |
Meyer |
No Injection |
0900-1300 |
measure SR converters in sectors 32, 33, 34, 35 |
Wang |
No beam |
1100-1300 |
Linac training (09-15) |
Thomas |
Limited injection |
1300-1400 |
Investigate change in S37 Cav2 Tuning Loop |
Berenc |
No beam |
1300-1500 |
Booster training (09-15) |
Karl |
Limited Injection |
1500-1900 |
Test P0 feedback |
Yao, DiMonte |
Stored Beam & Inj. |
1900-2400 |
Remeasuring P1 offsets and install new BPLD limits |
Decker, Hahne |
Stored Beam & Inj. |
2300-2400 |
PEM steering software tests |
Emery |
Stored Beam & Inj. |
|
Wednesday, 12/3/08 |
|
|
0000-0300 |
PEM steering software tests |
Emery |
Stored Beam & Inj. |
0300-0500 |
measure step response of "slow" correctors using RTFB corrector errors |
Emery |
Stored Beam & Inj. |
0500-0700 |
Storage Ring training (2300-0700) |
Fystro |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |