Machine Studies
Draft Schedule for Run01-1, 2009
January 21st 0800 – January 28th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 1/20/09 |
|
|
|
RF conditioning |
OPS |
Stored beam & Injection |
|
Wednesday, 1/21/09 |
|
|
0800-1200 |
BPLD validation. |
Bui |
Stored beam & Injection |
1200-1400 |
SR training. |
Karl |
Stored beam & Injection |
1200-1300 |
Linac training. Parallel to SR training. |
Weyer |
Occasional injection |
1300-1400 |
Linac training. Parallel to SR training. |
Thomas |
Occasional injection |
1400-1800 |
Xbpm checkout |
Hahne |
Stored beam & Injection |
1800-2400 |
BPM system checkout including A:P3. |
Decker Erwin Shang Lenkszus |
Stored beam & Injection |
|
Thursday, 1/22/09 |
|
|
0000-0200 |
BPM system checkout, continued. |
Decker Erwin Shang Lenkszus |
Stored beam & Injection |
0200-0400 |
SR training. |
Fystro |
Stored beam & Injection |
0400-0700 |
OPEN |
|
|
0700-1100 |
CPU correction. |
Xiao Emery |
Stored beam & Injection |
1100-1300 |
Linac training. |
Weyer |
Occasional injection |
1300-1500 |
Linac training. |
Thomas |
Occasional injection |
1100-1300 |
SR training. |
Karl |
Stored beam & Injection |
1500-2300 |
Orbit recovery. |
Decker Sajaev Emery |
Stored beam & Injection |
2300-2400 |
Sextupole offset measurement using response matrix. |
Sajaev Xiao |
Stored beam & Injection |
|
Friday, 1/23/09 |
|
|
0000-0500 |
Sextupole offset measurement using response matrix (continued). |
Sajaev Xiao |
Stored beam & Injection |
0500-0700 |
SR training. |
Fystro |
Stored beam & Injection |
0700-0900 |
Setup and test new orbit correction in PAR. |
Yao |
Stored beam & Injection |
0800-1200 |
PSS shutter checkouts. |
SI group |
No SR beam |
0800-1200 |
Radiation survey of RF systems. |
Vacca |
Zone E access |
0800-1200 |
Converter measurements. |
PS group |
|
0900-1030 |
Linac training. |
Meyer |
|
1030-1200 |
Linac traning. |
Thomas |
|
1200-1400 |
SR training. |
Karl |
Stored beam & Injection |
1400-2200 |
Prepare Xbpms for operation. |
Decker Hahne |
Stored beam & Injection |
1400-1800 |
Reconfigure and verify P0 feedback FPGA. Parallel to xbpm checkout. |
Yao |
No effect on beam |
2200-2400 |
Cerenkov detector studies. |
Yang |
Stored beam & Injection |
|
Saturday, 1/24/09 |
|
|
0000-0400 |
Cerenkov detector studies (continued). |
Yang |
Stored beam & Injection |
0400-0600 |
SR training. |
Fystro |
Stored beam & Injection |
0600-0800 |
PEM testing with beam. |
OPS |
Stored beam & Injection |
0800-2400 |
OPEN
|
|
|
|
Sunday 1/25/09 |
|
|
0000-0900 |
OPEN
|
|
|
0900-1700 |
RF bpm studies at S35. |
Decker Singh |
Stored beam & Injection |
1700-2400 |
Operational topup readiness test. |
OPS |
Stored beam & Injection |
|
Monday 1/26/09 |
|
|
0000-0800 |
OPEN
|
|
|
0800-0900 |
RF waveguide switch |
RF group |
No beam |
0900-1700 |
RF bpm studies at S35. |
Decker Singh |
Stored beam & Injection |
1700-1900 |
HOM spectra measurements. |
Harkay |
Stored beam & Injection |
1900-2400 |
Close-loop study of P0 feedback system. |
Yao Sajaev |
Stored beam & Injection |
|
Tuesday 1/27/09 |
|
|
0000-0100 |
Close-loop study of P0 feedback system. |
Yao Sajaev |
Stored Beam & Injection |
0100-0800 |
OPEN
|
|
|
0800-1000 |
Final pin-hole alignment. |
Yang |
Stored Beam & Injection |
1000-1300 |
Datapool stability at higher gains and shorter intervals. |
Emery |
Stored Beam & Injection |
1300-1700 |
CPU correction. |
Xiao Emery |
Stored Beam & Injection |
1700-1900 |
Optimize injection. |
Emery Sajaev Xiao |
Stored Beam & Injection |
1900-2200 |
Model measurements. |
Sajaev Xiao |
Stored Beam & Injection |
2200-2400 |
Reference lattice response matrix measurements. |
Sajaev |
Stored beam & Injection |
|
Wednesday 1/28/09 |
|
|
0000-0600 |
OPEN
|
|
|
0600-0800 |
Prepare for user Operations (24 singlets – Top-Up) |
OPS |
Stored beam & Injection |