Machine Studies
Draft Schedule for Run01-10, 2009
March 31st 0800 – April 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 3/31/09 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1030 |
S38 BPM integration |
Lenkszus |
No Beam |
0900-1000 |
Switch leaking pump P-405/P-SR-02A to P-404/P-SR-02B (Sectors 1&2) |
Furst/Theres |
No Beam |
0900-1100 |
Connect scope and logic analyzer to 36AH2 |
Fors |
No Beam |
0930-1030 |
Restore S2 striplines |
Gold/Yao |
Access zone A |
0900-1100 |
Injector training (09-15) |
Weyer |
Limited Injection |
1030-1100 |
Test PAR bunch cleaning bucket shifting problem (will coordinate with Weyer training) |
Yao, Grelick |
Occasional Injection |
1100-1300 |
SR training (09-15) |
Karl |
Stored Beam & Injection (not concurrent w/ Injector training) |
1100-1300 |
Injector training (09-15) |
Thomas |
Limited Injection (can be parasitic to SR training) |
1300-1500 |
DBPLD validation procedure training/verification |
Bui |
Stored beam & injection |
1500-1600 |
Linac studies |
Pasky |
Injection possible |
1500-1700 |
Observe transverse and longitudinal instability waveforms on the VSA using the sector 3 stripline sum signal. |
Harkay |
Stored beam & occasional injection |
1700-2100 |
CPU Alignment measurement |
Xiao |
Stored beam |
2000-2100 |
Set-up bunch purity with PAR RF System #2 |
Yao |
Occasional injection |
2100-2400 |
Measure single bunch threshold with or without running P0 feedback. |
Yao, Emery |
Stored beam & injection |
|
Wednesday, 4/1/09 |
|
|
0000-0100 |
Measure single bunch threshold with or without running P0 feedback. |
Yao, Emery |
Stored beam & injection |
0100-0700 |
BPM Noise studies Top-up (0100-0600) and Occasional injection (6-700) |
Decker |
Stored beam & injection |
0600-0700 |
Linac Studies |
Pasky |
Occasional Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |