Machine Studies

Schedule for Run01-11, 2009

April 7th 0800 – April 8th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, 4/7/09



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1100

MSB and LSB tests on S36A:H2:PS

Fors

No beam

0900-1100

Thermal scan Zone B & C PS

Puttkammer

No Beam

0900-1230

Measure fundamental-frequency coupling on the SR cavity HOM pickup lines.

Berenc/ Harkay

No Beam

0930-1000

6-ID PSS End-to-End Test

Hawkins

No beam

0930-1130

Resolve 8-ID Safety Shutter No Switch Faults

SI Group

Access Zone A

0930-1130

Install cables between S2 and S4, S3 and S4 for P0 feedback work

Gold/Yao

No beam

0930-1130

Swap out thyratron trigger boards P4EK

PS group

Access PAR

0930-1000

Check for water leaks in Linac/PAR

Theres, Bechtold

Access Linac/ PAR

1130-1200

Recover Linac

OPS

No beam

1200-1330

Injector training (09-15)

Weyer

Limited injection

1230-1330

Test bunch current monitor

Yao/Lenkszus

Stored beam

1330-1500

SR training (09-15)

Karl

Stored Beam & Injection

1500-1800

Transverse instability studies using FPGA and VSA, 24 singlets, top-up

Harkay, Yao

Stored beam & injection

1800-2000

Set-up hybrid lattice for P0 feedback studies

Sajaev

Stored beam & injection

1800-2000

Set-up P0 feedback for hybrid measurements (parasitic to setting up hybrid lattice

Yao

Parasitic

2000-2200

Make measurement with chromaticity scan

Sajaev, Yao

Stored beam & injection

2200-2300

Remove 2-sector bump to steer 19-ID closer to desired orbit

Sajaev

Stored beam

2300-2400

BPLD occurrence study

Sajaev

Stored beam & injection


Wednesday, 4/8/09



0000-0200

Restore and measure optics for RHB lattice

Sajaev

Stored beam & injection

0200-0500

CPU multipole center measurements

Xiao

Stored beam

0500-0700

OPEN



0700-0800

Prepare for User beam

OPS

Stored Beam & Injection