Machine Studies
Schedule for Run01-8, 2009
March 17th 0800 – March 18th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, 3/17/09 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1030 |
RTFB studies |
Lenkszus |
No Beam |
0900-1700 |
AHU studies |
Stevens/Doose |
No requirements |
0900-0930 |
Install patch cable to connect S3BP5 to hybrids panel on the same rack. |
Gold |
No impact |
0900-0930 |
Reboot iocs37vp |
Xu |
No beam |
1030-1100 |
Recover SR beam. |
OPS |
Stored Beam & Injection |
1100-1300 |
Test chirp+demodulation of tune FPGA box. |
Yao |
Stored Beam & Injection |
1300-1500 |
Test S3B:P5 signal for tune measurement. |
Yao Gold |
Stored Beam & Injection |
1500-1900 |
CPU AC correction. |
Xiao |
Stored Beam & Injection |
1500-1700 |
Injector training. Parallel to CPU correction. |
Weyer |
Limited Injection |
1900-2100 |
SR training. |
Karl |
Stored Beam & Injection |
2100-2400 |
Sextupole offset measurements using response matrices. |
Sajaev |
Stored Beam & Injection |
|
Wednesday, 3/18/09 |
|
|
0000-0200 |
Sextupole offset measurement (continued). |
Sajaev |
Stored Beam & Injection |
0200-0500 |
Reference lattice measurements. |
Sajaev |
Stored Beam & Injection |
0500-0700 |
Injector training. |
Thomas |
Limited Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |