Machine Studies
Schedule for Run02-7, 2009
July 14th 0800 – July 15th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, July 14, 2009 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1100 |
Map Linac vacuum levels |
Pasky |
Limited Injection |
0930-1000 |
check fastener tightness on the RF4 and RF5 13.2kV fused-disconnect switch door latches |
RF Group |
No beam |
0900-1100 |
Troubleshoot S36 rack power supply |
Pietryla |
No Beam |
0930-1030 |
8BM PSS end to end test |
Boron |
No Beam |
1030-1100 |
Patch the attenuator for the bunch current monitor to optimize input signal level |
Lenkszus/ Gold |
No impact |
1100-1300 |
SR Requalification |
Labuda/ Schroeder |
Stored beam & injection |
1100-1300 |
Test S35 stripline and amplifiers. (parasitic to SR Requal) |
Yao/Gold |
No impact |
1300-1500 |
Injector training (09-15) |
Thomas |
Limited injection |
1300-1500 |
test chromaticity measurement script. |
Yao/Shang/ Xiao |
Stored beam & Occ. Injection |
1500-1700 |
Measurements with Lee Teng's students |
Harkay, et all |
Stored beam & Occ. Injection |
1700-1900 |
Investigation of S35 DCCT Abnormal Imax Signal |
Chae/Keane/ Yao |
Stored beam |
1730-1930 |
PAR bunch length measurment. PAR beam with varied charge. Can provide injection. |
Yao, Harkay |
PAR beam |
1930-2230 |
Bunch-by-bunch tune measurement |
Harkay |
Stored beam & inj. |
2230-2400 |
Optimize injection for new hybrid sextupoles |
Sajaev |
Stored beam & inj. |
|
Wednesday, July 15, 2009 |
|
|
0000-0230 |
Optimize injection for new hybrid sextupoles (continued) |
Sajaev |
Stored beam & inj. |
0230-0430 |
Investigate beam loss during magnet ramp from 24 singlets lattice to hybrid |
Sajaev |
Stored beam & inj. |
0430-0630 |
Turn-by-turn measurements using S38 FPGA bpms |
Sajaev |
Stored beam & inj. |
0630-0700 |
OPEN |
|
|
0700-0800 |
Prepare for user Operations |
Ops |
Stored Beam & Injection |