Machine Studies
Schedule for Run02-9, 2009
July 28th 0800 – July 29th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, July 28, 2009 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1300 |
Remove backscatter beamline |
Kruy |
No Beam |
0930-1000 |
11-ID PSS End-to-End test |
Hawkins |
No beam |
1000-1200 |
test the use of gated integration which is enabled during the PAR RF pulse and disabled between pulses |
Grelick, Berenc, Smith, DiMonte |
Limited Injection |
1200-1300 |
Test DSP code |
Lenkszus |
No Beam |
1300-1400 |
Shielding verification after removal of backscatter beamline |
Vacca |
Stored beam |
1400-1700 |
FPGA software testing |
Decker/Shang |
Stored beam & Occ. injection |
1500-1700 |
Test Par bunch length measurement application |
Yao |
Limited injection |
1700-2100 |
Test current threshold with feedback (24 singlet fill) |
Yao |
Stored beam & injection |
2100-2300 |
Storage Ring requalification |
Flood, S. |
Stored beam & injection |
2300-2400 |
Punch down ID4 correctors |
Sajaev |
Stored beam & Injection |
|
Wednesday, July 29, 2009 |
|
|
0000-0500 |
setup 24 singlets with old quads and new sextupoles |
Sajaev |
Stored beam & injection |
0500-0700 |
Injector training (23-07) |
Weyer |
Limited Injection |
0700-0800 |
Prepare for user Operations |
Ops |
Stored Beam & Injection |