Machine Studies

Draft Schedule for Run03-1, 2009

September 29th 0800 – October 6th 0800

Time

Descriptions

Studiers

SR Status


Monday, September 28, 2009




RF conditioning to 120 mA

OPS



Cerenkov detector measurements. Parallel to RF conditioning.

Yang



Pinhole camera commissioning. Parallel to RF conditioning.

Yang



Tuesday, September 29, 2009



1000-1600

BPLD validation.

Bui

Stored Beam & Injection

1200-1400

Booster training. Parallel to BPLD validation.

Weyer

Occasional injection

1600-1800

BM xbpm checkout.

Hahne

Stored Beam & Injection

1600-1800

Set up bunch cleaning. Parallel to bpm checkout.

Yao

Occasional injection

1800-2200

ID xbpm checkout.

Hahne

Stored Beam & Injection

1800-2200

Calibrate gap voltage reading for PAR. Parallel to xbpm checkout.

Yao

Occasional injection

2200-2400

Setup and test gentle beam dump.

Sajaev Emery

Stored Beam & Injection


Wednesday, September 30, 2009



0000-0200

Booster training.

Thomas

Occasional injection





0200-1100

Booster Dipole troubleshooting

PS Group

No injection

0700-1100

Make new files for linac beam operation. Parallel to BPLD validation.

Pasky

No injection

0800-0830

Prepare for access

OPS, FMS

No Beam

0830-0930

Repair loss monitor cable

Yao, Gold

Access Zone F

0830-0900

Switch to RF-1/3

Horan

No Beam

0830-1030

Repair S35 Digital Camera

Yang

No Beam

1100-1900

Initial bpm system checkout.

Decker

Stored Beam & Injection

1100-1300

Booster training.

Weyer

Occasional injection

1900-2400

Orbit recovery.

Decker Sajaev

Stored Beam & Injection


Thursday, October 01, 2009



0000-0300

Orbit recovery (continued).

Decker Sajaev

Stored Beam & Injection

0300-0700

Correct beta functions.

Sajaev Xiao

Stored Beam & Injection

0300-0500

Booster training. Parallel to correct beta functions.

Thomas

Occasional injection

0700-1100

Narrow-band bpm external clock commissioning.

Sun Erwin Lill

Stored Beam & Injection

1100-1700

Commission P0 feedback with remote DAC.

Yao DiMonte

Stored Beam & Injection

1100-1300

Booster training. Parallel to P0 feedback.

Weyer

Occasional injection

1700-2300

Cerenkov detector initial setup.

Yang

Stored Beam & Injection

2300-2400

Bunch-by-bunch tune shift measurement.

Chae Harkay

Stored Beam & Injection


Friday, October 02, 2009



0000-0500

Bunch-by-bunch tune shift (continued).

Chae Harkay

Stored Beam & Injection

0500-0700

Booster training.

Thomas

Occasional injection

0700-0800

Reboot ioclic1 & ioclic4

Pietryla


0730-0800

Prepare for access

OPS

No beam

0800-0900

Repair S35 pinhole camera

Yang

Zone F Access

0800-1800

Booster Dipole repair (1200-1800 parasitic to CPU check-out)

PS Group

Limited Injection

0800-1200

PSS shutter checkouts

SI group

No Beam

0800-1200

Continue with making new files for Linac Operation

Pasky

Limited Injection

0800-1200

SR Dipole check-out

PS Group

No beam

0800-0900

Switch to RF-2/4

Horan

No Beam

0900-0930

Recover from Zone F Access

OPS

No beam

1200-1800

CPU checkout.

Xiao

Stored Beam & Injection

1800-2100

OPEN



2100-2400

Cerenkov detector commissioning, phase 2.

Yang

Stored Beam & Injection


Saturday, October 03, 2009



0000-0500

Cerenkov detector commissioning (continued).

Yang

Stored Beam & Injection

0500-0900

OPEN



0900-1500

Continue with Booster Dipole investigation

PS Group

Limited injection

1500-1900

P0 feedback beam test.

Yao

Stored Beam & Injection

1900-2400

Topup verification.

OPS

Stored Beam & Injection


Sunday, October 04, 2009



0000-0200

Topup verification (continued).

OPS

Stored Beam & Injection

0000-1000

OPEN



1000-1300

HOM archiving.

Harkay

Stored Beam & Injection

1300-1600

Alternate hybrid mode setup (without 16mA bunch)

Harkay

Stored Beam & Injection

1600-2400

ID26 beam checkout.

ID26

Stored Beam & Injection


Monday, October 05, 2009



0000-0700

OPEN



0700-0900

Booster training.

Thomas

Occasioanl injection

0900-1100

Booster training.

Weyer

Occasional injection

1100-1300

SR fast corrector noise study.

Yao

Stored Beam & Injection

1300-2100

Final bpm system checkout.

Decker

Stored Beam & Injection

2100-2400

Final setup of S35 diagnostics.

Yang

Stored Beam & Injection


Tuesday, October 06, 2009



0000-0100

Final setup of S35 diagnostics (continued)

Yang

Stored Beam & Injection

0100-0500

Optimize injection.

Sajaev Xiao

Stored Beam & Injection

0500-0630

OPEN



0630-0800

Prepare for user Operations (24 singlets – Top-Up)

Ops

Stored Beam & Injection