Draft Schedule for Run03-1, 2009
September 29th 0800 – October 6th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, September 28, 2009 |
|
|
|
RF conditioning to 120 mA |
OPS |
|
|
Cerenkov detector measurements. Parallel to RF conditioning. |
Yang |
|
|
Pinhole camera commissioning. Parallel to RF conditioning. |
Yang |
|
|
Tuesday, September 29, 2009 |
|
|
1000-1600 |
BPLD validation. |
Bui |
Stored Beam & Injection |
1200-1400 |
Booster training. Parallel to BPLD validation. |
Weyer |
Occasional injection |
1600-1800 |
BM xbpm checkout. |
Hahne |
Stored Beam & Injection |
1600-1800 |
Set up bunch cleaning. Parallel to bpm checkout. |
Yao |
Occasional injection |
1800-2200 |
ID xbpm checkout. |
Hahne |
Stored Beam & Injection |
1800-2200 |
Calibrate gap voltage reading for PAR. Parallel to xbpm checkout. |
Yao |
Occasional injection |
2200-2400 |
Setup and test gentle beam dump. |
Sajaev Emery |
Stored Beam & Injection |
|
Wednesday, September 30, 2009 |
|
|
0000-0200 |
Booster training. |
Thomas |
Occasional injection |
|
|
|
|
0200-1100 |
Booster Dipole troubleshooting |
PS Group |
No injection |
0700-1100 |
Make new files for linac beam operation. Parallel to BPLD validation. |
Pasky |
No injection |
0800-0830 |
Prepare for access |
OPS, FMS |
No Beam |
0830-0930 |
Repair loss monitor cable |
Yao, Gold |
Access Zone F |
0830-0900 |
Switch to RF-1/3 |
Horan |
No Beam |
0830-1030 |
Repair S35 Digital Camera |
Yang |
No Beam |
1100-1900 |
Initial bpm system checkout. |
Decker |
Stored Beam & Injection |
1100-1300 |
Booster training. |
Weyer |
Occasional injection |
1900-2400 |
Orbit recovery. |
Decker Sajaev |
Stored Beam & Injection |
|
Thursday, October 01, 2009 |
|
|
0000-0300 |
Orbit recovery (continued). |
Decker Sajaev |
Stored Beam & Injection |
0300-0700 |
Correct beta functions. |
Sajaev Xiao |
Stored Beam & Injection |
0300-0500 |
Booster training. Parallel to correct beta functions. |
Thomas |
Occasional injection |
0700-1100 |
Narrow-band bpm external clock commissioning. |
Sun Erwin Lill |
Stored Beam & Injection |
1100-1700 |
Commission P0 feedback with remote DAC. |
Yao DiMonte |
Stored Beam & Injection |
1100-1300 |
Booster training. Parallel to P0 feedback. |
Weyer |
Occasional injection |
1700-2300 |
Cerenkov detector initial setup. |
Yang |
Stored Beam & Injection |
2300-2400 |
Bunch-by-bunch tune shift measurement. |
Chae Harkay |
Stored Beam & Injection |
|
Friday, October 02, 2009 |
|
|
0000-0500 |
Bunch-by-bunch tune shift (continued). |
Chae Harkay |
Stored Beam & Injection |
0500-0700 |
Booster training. |
Thomas |
Occasional injection |
0700-0800 |
Reboot ioclic1 & ioclic4 |
Pietryla |
|
0730-0800 |
Prepare for access |
OPS |
No beam |
0800-0900 |
Repair S35 pinhole camera |
Yang |
Zone F Access |
0800-1800 |
Booster Dipole repair (1200-1800 parasitic to CPU check-out) |
PS Group |
Limited Injection |
0800-1200 |
PSS shutter checkouts |
SI group |
No Beam |
0800-1200 |
Continue with making new files for Linac Operation |
Pasky |
Limited Injection |
0800-1200 |
SR Dipole check-out |
PS Group |
No beam |
0800-0900 |
Switch to RF-2/4 |
Horan |
No Beam |
0900-0930 |
Recover from Zone F Access |
OPS |
No beam |
1200-1800 |
CPU checkout. |
Xiao |
Stored Beam & Injection |
1800-2100 |
OPEN |
|
|
2100-2400 |
Cerenkov detector commissioning, phase 2. |
Yang |
Stored Beam & Injection |
|
Saturday, October 03, 2009 |
|
|
0000-0500 |
Cerenkov detector commissioning (continued). |
Yang |
Stored Beam & Injection |
0500-0900 |
OPEN |
|
|
0900-1500 |
Continue with Booster Dipole investigation |
PS Group |
Limited injection |
1500-1900 |
P0 feedback beam test. |
Yao |
Stored Beam & Injection |
1900-2400 |
Topup verification. |
OPS |
Stored Beam & Injection |
|
Sunday, October 04, 2009 |
|
|
0000-0200 |
Topup verification (continued). |
OPS |
Stored Beam & Injection |
0000-1000 |
OPEN |
|
|
1000-1300 |
HOM archiving. |
Harkay |
Stored Beam & Injection |
1300-1600 |
Alternate hybrid mode setup (without 16mA bunch) |
Harkay |
Stored Beam & Injection |
1600-2400 |
ID26 beam checkout. |
ID26 |
Stored Beam & Injection |
|
Monday, October 05, 2009 |
|
|
0000-0700 |
OPEN |
|
|
0700-0900 |
Booster training. |
Thomas |
Occasioanl injection |
0900-1100 |
Booster training. |
Weyer |
Occasional injection |
1100-1300 |
SR fast corrector noise study. |
Yao |
Stored Beam & Injection |
1300-2100 |
Final bpm system checkout. |
Decker |
Stored Beam & Injection |
2100-2400 |
Final setup of S35 diagnostics. |
Yang |
Stored Beam & Injection |
|
Tuesday, October 06, 2009 |
|
|
0000-0100 |
Final setup of S35 diagnostics (continued) |
Yang |
Stored Beam & Injection |
0100-0500 |
Optimize injection. |
Sajaev Xiao |
Stored Beam & Injection |
0500-0630 |
OPEN |
|
|
0630-0800 |
Prepare for user Operations (24 singlets – Top-Up) |
Ops |
Stored Beam & Injection |