Machine Studies
Schedule for Run01-12, 2010
April 20th 0800 – April 21st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, April 20, 2010 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0910 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0910-0930 |
RF waveguide switch |
Horan |
No Beam |
0910-1000 |
Replace fan at S:IK3 |
Puttkammer |
No Beam |
0930-1130 |
Remove upstream 1ID |
Grimmer |
Access Zone A |
1130-1200 |
Recover SR systems |
OPS |
Stored Beam & Injection |
1200-1300 |
Verify RF2 able to support beam and switch back to RF3 |
RF Group/Ops |
Stored Beam & Inj. |
1300-1400 |
SR Training |
Pasky/Schroeder |
Stored Beam & Inj. |
1400-1600 |
Set-up new S23 RHB lattice |
Xiao/Emery |
Stored beam & inj. |
1600-2200 |
Test S23 RHB lattice (shutters open) |
S23 beamline personnel |
Stored Beam & inj. |
2200-2400 |
Switch lattice and recover orbit for 324 Singlets |
Xiao/Sajeav |
Stored Beam & inj. |
|
Wednesday, April 21, 2010 |
|
|
0000-0230 |
Switch lattice and recover orbit for 324 Singlets |
Xiao/Sajaev |
Stored Beam & inj. |
0230-0630 |
measure P0 feedback accumulation limit and damping time |
Yao |
Stored Beam & occ. inj. |
0630-0800 |
Prepare for User beam (324 singlets) |
OPS |
Stored Beam & Injection |