Draft Schedule for Run01-2, 2010
February 9th 0800 - February 10th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 09, 2010 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1000 |
Troubleshoot iocs25fb |
Lenkszus |
No Beam |
0900-1100 |
CPU IOC reboot /slew rate adjustment |
Smith/Deriy |
No Beam |
0900-1100 |
Swap S17AS3, troubleshoot BTS:AH1, replace dump resistor on SR 4:5 T2 |
Puttkammer |
No Beam |
0900-1100 |
Reboot ioclet2bpm and test iocConsole |
Pietryla |
No Beam |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Wednesday, February 10, 2010 |
|
|
|
|
|
|
|
|
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |