Machine Studies
Draft Schedule for Run01-3, 2010
February 16th 0800 - February 17th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 16, 2010 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-0930 |
Reboot iocruncontrol |
Xu |
No Beam |
0900-1100 |
B:BM resonant filter study |
Feng |
Limited Injection (continuous injection during TLD exposure) |
0900-1200 |
CPU software debugging |
Deriy, Smith M. |
No Beam |
0900-1300 |
Linac/PAR only 09:00-11:00, Linac/PAR/ Booster 11:00/13:00 |
Pasky |
Limited Injection (continuous injection during TLD exposure) |
0930-1000 |
PSS end to end tests at 7ID & 14BM |
Boron |
No Beam |
0930-1000 |
Insert TLDs at SR:IS1 |
Dooling |
Access Zone F |
0930-1100 |
Investigate suspected problem with S36 PLC Interlock system |
Horan |
No beam |
1015-1030 |
Expose TLDs at SR:IS1 |
Dooling |
Beam only up to SR:IS1 (Zone F PS and RF remain locked out) |
1030-1100 |
Retrieve TLDs from SR:IS1 |
Dooling |
Access Zone F |
1200-1300 |
Test/collect FPGA bpm data |
Wang/Shang |
Stored beam |
1300-1400 |
Storage ring training |
Pasky/ Schroeder |
Stored beam & injection |
1400-1600 |
Injection into small dynamic aperature |
Emery |
Stored beam & injection |
1600-2200 |
Fine tune of CPU AC mode - Vertical orbit and coupling |
Xiao |
Stored beam |
1700-2100 |
PAR High Current Studies |
Yao, Harkay Chae |
Occasional Inj. available |
2100-2400 |
Measure beam emittance and rms motion with P0 feedback loops closed & feedback study with negative chromaticity |
Chae, Yao |
Stored beam & inj. |
|
Wednesday, February 17, 2010 |
|
|
0000-0300 |
Measure beam emittance and rms motion with P0 feedback loops closed & feedback study with negative chromaticity |
Chae, Yao |
Stored beam & inj. |
0300-0700 |
BPM Studies (Top-up desired) |
Decker, Xu |
Stored beam & injection |
0300-0700 |
Cherenkov detector studies (compatible with above study) |
Yang |
Stored beam |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |