Machine Studies
Schedule for Run03-10, 2010
December 7th 0800 – December 8th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, December 07, 2010 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/ OPS |
Stored Beam & Injection |
0900-1030 |
Removal of waveguide blanking plate at flange RFTS118 |
Horan |
No Beam |
0930-1000 |
End to end test of 23ID |
Forrestal |
No Beam |
0930-1030 |
Troubleshoot 9BM PS2 Close Switch Fail |
Banks |
Access Zone B |
0930-1130 |
Install BLM near BTX dump |
Erwin |
Access Booster |
1030-1300 |
Phase noise measurements in parallel |
Horan |
No Beam |
1200-1300 |
Add hardware in iocs19bpm (powered down) for narrowband synchronous timing study |
Lenkszus |
No beam |
1300-1600 |
Collect data for Narrowband BPMs with synchronous timing for hybrid fill pattern. |
Bui |
Stored beam & inj. |
1300-1600 |
Test new booster ramp correction script |
Yao |
Injection possible |
1600-1700 |
Retime S38 bpms |
Decker/Bui |
Stored beam & inj. |
1700-1900 |
Single bunch gas bremsstrahlung intensity measurements (hybrid lattice) |
Yang/ Dooling |
Stored beam & inj. |
1900-2400 |
324 set-up and orbit switch |
Xiao |
Stored beam & inj |
|
Wednesday, December 08, 2010 |
|
|
0000-0100 |
324 set-up and orbit switch (continued) |
Xiao |
Stored beam & inj. |
0100-0630 |
APS-U lattice |
Emery/Xiao |
Stored beam & inj. |
0630-0800 |
Prepare for User beam (324 singlets) |
OPS |
Stored Beam & Injection |