Machine Studies
Draft Schedule for Run03-12, 2010
December 21st 0800 - December21st 2400
|
Time |
Descriptions |
Studiers |
SR Status |
|
|
Tuesday, December 21, 2010 |
|
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
|
0810-0845 |
Set-up for 150mA study / ACIS shutdown validate SR RF1 HVPS |
Schroeder/OPS |
No beam |
|
0845-1700 |
Bremsstrahlung studies using 35-ID (150mA) |
Yang/Dooling |
Stored beam & injection |
|
1700-1800 |
Return to 24 singlets, tune-up injection if necessary |
OPS |
Stored beam & inj. |
|
1800-2200 |
Verify Top-up at 150mA |
OPS |
Stored beam & injection |
|
2200-2400 |
Gentle shutdown of SR PS and RF systems |
OPS |
No beam |