Machine Studies

Schedule for Run01-4, 2011

February 22nd 0800 - February 23rd 0800



Time

Descriptions

Studiers

SR Status


Tuesday, February 22, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-1100

Install waveguide shorting flange

RF group

No Beam

0900-1100

Install new phase shifter card at RF-3

RF group

No Beam

0900-1300

Troubleshoot RF5

RF Group

No beam

0900-1100

Troubleshoot L1:RG1:SC1:HZ P.S.

Hillman

No beam

0900-1100

Corrector power supply testing

Lenkszus

No Beam

0900-1100

Investigate/swap S5A:Q5 & S14B:S1

Puttkammer

No Beam

0900-1100

Investigate magnet temperature readback failures

Sprau

No Beam

0900-0920

Validate linac laser safety shutter

Dooling/Pasky

No beam

0920-1100

PCGun tests with PAR in 1 Hz mode

Sereno

No Injection

1000-1100

Swap S3A:Q5 power supply

Vargas

No Beam

1100-1300

Troubleshoot 60Hz ripple in RF4 anode current

RF group

Stored beam

1100-1300

Linac training (parallel to RF4 troubleshooting).

Mazzio

Limited injection

1300

Fill 324 bunches.

OPS


1300-1600

Test SF noise pickup from BM ramp.

Wang Feng Yao

No injection

1300-1500

Set-up PAR Rf harmonic system #1 without beam

RF Group

No injection

1300-1400

Replace RF2 modulator beacon

Cours

No injection

1500-1600

Check Par RF Harmonic system #1 with beam and make new reference files/Check Par Fundamental system #1

Yao

Limited injection

1300-1700

Measure BPM offsets (parallel to Booster work).

Sajaev

Stored beam

1600-1800

Set up and test controllaw-based bcontrol.

Yao Shang

Limited injection

1700-2000

Test large local steering in 2BM (parallel to Booster work).

Xiao

Stored beam

1800-2000

Check and optimize PTB trajectory.

Yao

Limited injection

2000-2200

Measure booster chromaticity.

Yao

No SR beam

2200-2400

Install bpm offsets.

Sajaev

Stored Beam & Injection


Wednesday, February 23, 2011



0000-0200

Test failed sextupole correction.

Sajaev

Stored Beam & Injection

0200-0500

Complete set up of APS-U for high-current test.

Sajaev

Stored Beam & Injection

0500-0700

DA measurement for comparison with model for CDR.

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection