Machine Studies
Schedule for Run01-4, 2011
February 22nd 0800 - February 23rd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 22, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1100 |
Install waveguide shorting flange |
RF group |
No Beam |
0900-1100 |
Install new phase shifter card at RF-3 |
RF group |
No Beam |
0900-1300 |
Troubleshoot RF5 |
RF Group |
No beam |
0900-1100 |
Troubleshoot L1:RG1:SC1:HZ P.S. |
Hillman |
No beam |
0900-1100 |
Corrector power supply testing |
Lenkszus |
No Beam |
0900-1100 |
Investigate/swap S5A:Q5 & S14B:S1 |
Puttkammer |
No Beam |
0900-1100 |
Investigate magnet temperature readback failures |
Sprau |
No Beam |
0900-0920 |
Validate linac laser safety shutter |
Dooling/Pasky |
No beam |
0920-1100 |
PCGun tests with PAR in 1 Hz mode |
Sereno |
No Injection |
1000-1100 |
Swap S3A:Q5 power supply |
Vargas |
No Beam |
1100-1300 |
Troubleshoot 60Hz ripple in RF4 anode current |
RF group |
Stored beam |
1100-1300 |
Linac training (parallel to RF4 troubleshooting). |
Mazzio |
Limited injection |
1300 |
Fill 324 bunches. |
OPS |
|
1300-1600 |
Test SF noise pickup from BM ramp. |
Wang Feng Yao |
No injection |
1300-1500 |
Set-up PAR Rf harmonic system #1 without beam |
RF Group |
No injection |
1300-1400 |
Replace RF2 modulator beacon |
Cours |
No injection |
1500-1600 |
Check Par RF Harmonic system #1 with beam and make new reference files/Check Par Fundamental system #1 |
Yao |
Limited injection |
1300-1700 |
Measure BPM offsets (parallel to Booster work). |
Sajaev |
Stored beam |
1600-1800 |
Set up and test controllaw-based bcontrol. |
Yao Shang |
Limited injection |
1700-2000 |
Test large local steering in 2BM (parallel to Booster work). |
Xiao |
Stored beam |
1800-2000 |
Check and optimize PTB trajectory. |
Yao |
Limited injection |
2000-2200 |
Measure booster chromaticity. |
Yao |
No SR beam |
2200-2400 |
Install bpm offsets. |
Sajaev |
Stored Beam & Injection |
|
Wednesday, February 23, 2011 |
|
|
0000-0200 |
Test failed sextupole correction. |
Sajaev |
Stored Beam & Injection |
0200-0500 |
Complete set up of APS-U for high-current test. |
Sajaev |
Stored Beam & Injection |
0500-0700 |
DA measurement for comparison with model for CDR. |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |