Machine Studies
Schedule for Run01-6, 2011
March 8th 0800 – March 9th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, March 08, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1300 |
Replace klystron at RF-1 |
Horan |
No Beam |
0900-1100 |
Terminate cables in L1:IC1 |
Pietryla |
Limited Injection |
0900-1100 |
Repair magent temp readback issues in Zone B |
Puttkammer |
No Beam |
0900-1130 |
Connect piping from the new rf gun water stations through to the ITS |
Wright |
Access to Linac |
11300-1300 |
Develop and test PAR RF12 tuner FF setup tool. |
Harkay Yao |
PAR beam |
1300-1500 |
Investigate transition thresholds for ID gap feedforward. |
Schroeder |
Stored Beam & Injection |
1500-1700 |
Steer beam for BM2. Shutter open. |
Xiao |
Stored Beam & Injection |
1700-1900 |
Correct optics after BM2 steering. |
Xiao |
Stored Beam & Injection |
1900-2400 |
BPM studies. |
Decker |
Stored Beam & Injection |
|
Wednesday, March 09, 2011 |
|
|
0000-0100 |
BPM studies (continued). |
Decker |
Stored Beam & Injection |
0100-0300 |
Measure booster chromaticity. |
Yao |
No SR beam |
0300-0400 |
Test coupling correction. |
Sajaev |
Stored Beam & Injection |
0400-0600 |
Diagnose RTFB feedforward problem. |
Lenkszus Sajaev |
Stored Beam & Injection |
0600-0700 |
Collect FPGA bpm time response to a single corrector. |
Emery |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |