Machine Studies

Schedule for Run01-8, 011

March 22nd 0800 – March 23rd 0800



Time

Descriptions

Studiers

SR Status


Tuesday, March 22, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-0930

Reboot iocrf3hvps

DiMonte

No Beam

0900-1000

End to end tests at 13ID

Budz

No Beam

0900-1100

Check timing signals at S13

Laird

No Beam

0900-1100

Main Ramping voltage regulator testing

Wang

No Injection

0900-1100

Replace a Digitizer card in S15 feedback IOC crate (power cycle of IOCS15FB)

Erwin

No beam

0900-1100

Investigate BPLD circuit problem S32

Grimmer

No Beam

0900-1200

Repair magent temp readback issues in Zone B, C & D

Puttkammer

No Beam

0930-1330

Troubleshoot/repair RG-2 kicker

Hillman

Access Linac

1330-1500

Recover SR beam, inject 324 bunches, Linac training.

OPS

Stored Beam & Injection

1500-1700

Linac adjustments.

Pasky

Limited injection

1700-2000

Test PC gun to PAR injection.

Sereno

Limited injection

1400-1600

L1 shielding tests. Parasitic to other studies.

Cours

Stored Beam & Injection (parasitic study)

1400-1900

Measure BPM offsets.

Sajaev

Stored beam

2000-2400

Orbit switch.

Xiao

Stored Beam & Injection


Wednesday, March 23, 2011



0000-0200

Test PAR tunerFF script.

Harkay Yao

No injection

0200-0300

Optimize P0 feedback parameters.

Yao

Stored Beam & Injection

0300-0400

Measure booster chromaticity.

Yao

No SR beam

0400-0700

BPM studies.

Decker

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection