Machine Studies

Schedule for Run01-9, 011

March 29th 0800 – March 30th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, March 29, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-0930

Reboot interleaving PS

Puttkammer

No Injection

0900-1100

Re-terminate MPS fiber(s) in A014. Switch S27 MPS fiber to resolve issue related to recent beam dumps

Shoaf

No injection

0900-1200

B:BM current ripple measurement

Feng

No Injection

0900-1100

Repair temperature readbacks SR Zone D & E

Puttkammer

No Beam

0900-1100

Troubleshoot B:IK

Puttkammer

Limited Injection

0900-1100

Test CMPSI card in iocs39fb

Lenkszus

No Beam

0900-1100

Perform transfer function measurements on ACF100 cards

Horan

No Beam

0930-1130

Linac Training

Mazzio/Fystro

Limited injection

1130-1300

Linac training

Bogdan/Pasky

Limited injection

1100-1300

L1 shielding tests. Parasitic study.

Cours

Stored Beam & Injection

1200-1230

Recover SR beam

OPS

Stored Beam & Occ. Inj.

1300-1600

ID29 shielding verification

Ramanathan

Stored Beam & Injection

1600-2000

Fast ion effect study.

Chae Yao

Stored Beam & Injection

2000-2200

Measure tune shift due to P0 feedback.

Yao

Stored Beam & Injection

2200-2400

Measure booster bcontrollaw response matrices.

Yao

Stored Beam & Injection


Wednesday, March 30, 2011



0000-0200

Measure booster chromaticity.

Yao

Stored Beam & Injection

0200-0700

BPM studies.

Decker

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection