Machine Studies

Draft Schedule for Run02-4, 2011

June 21st 0800 - June 22nd 0800



Time

Descriptions

Studiers

SR Status


Tuesday, June 21, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-0930

Reboot siocfe34

Smith

Stored Beam & Injection

0900-1000

Install modified canted undulator PS in S23/24

Puttkammer

No Beam

0900-1000

Repair/replace VXI module in iocs27bpm

Lenkszus

No Injection

0900-1100

Investigate invalid thermocouple readings in ITS

Pietryla

No Impact to Injection

0900-1100

Switching between PAR rf systems... make files

Pasky

Limited Injection

0900-1100

Test new Phase Shifter module at RF4

Berenc

No Beam

0930-1130

Inspect and repair ground fault at B4C3H

Putnam

Access Booster

1130-1200

Recover injector systems & store beam/ verify no problems for modified canted undulator PS in S23/24

OPS

Stored Beam and Injection

1200-1300

Test beam dump recording

Sajaev/Emery

Stored beam & inj.

1300-1500

test and run boosterCorrectorBumpScan

Yao/Shang

Limited injection

1300-1600

investigating coupling perturbation caused by CPU

Emery

Stored beam

1600-1800

test DSP85 AC voltmeter corrector/bpm drive error response measurement and plotting script

Sereno/Shang

Stored beam

1600-1800

Injector training (15-23)

Mazzio

Limited injection

1800-2200

multibunch instability studies (0-100mA, 24 singlets, 324 singlets)

Harkay

Stored beam & inj.

2200-2400

Lifetime scan

Sajaev

Stored beam & inj.


Wednesday, June 22, 2011



0000-0400

Setup 4NLSS lattice

Sajaev

Stored beam & injection

0400-0700

BPM offset measurements

Sajaev

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection