Machine Studies

Schedule for Run02-9, 2011

July 25th 0800 - July 27th 0800



Time

Descriptions

Studiers

SR Status


Monday, July 25, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1130

Repair Johnson controls controller

Wright

No Beam

Affects SR sectors 13-14

0930-1130

P.S. thermal scans Zone C

P.S. Group

No beam

0930-1130

Remove blanking plate at flange RFTS118

Horan

No Beam

0930-1230

Investigate RF5 13.2kV disconnect dropout

RF group

No Beam

1000-1100

Adjust upstream flange at BNL bellows

Hoyt

Access Zone D

1000-1130

Phase shifter study for S37 LLRF crate

Berenc

No Beam

1130-1230

Install phase shifter at RF2

Berenc

No Beam

1230-1530

Slow beam dump by resonance crossing (rf frequency)

Chae/Yao

Stored beam & inj.

1530-1730

Make slow beam dump script

Sajaev/Chae

Stored beam & inj.

1730-1900

SR requalification

Fystro/ Schroeder

Stored beam & injection

1900-2400

P2 offsets measurement

Xiao/Boon/ Harkay

Stored beam & injection


Tuesday, July 26, 2011



0000-0400

Coupling correction

Sajaev

Stored beam & inj.

0400-1000

measure fast corrector's transfer

function and open loop/close loop PSD in RTFB system

Lenkszus/Xu

Stored beam & injection

1000-1100

4-ID-D Radiation Survey with White Beam

Wyncott

Stored beam

1100-1300

measure booster chromaticity and BPM response (will be making large changes in frequency)

Yao

No SR beam

1300-1700

Orbit Switch

Xiao

Stored beam & inj.

1700-1800

Set-up P0 feedback with 24 singlets

Yao

Stored beam & inj.

1800-2400

6BM steering studies for SCU0 (24 singlets, 100mA)

Harkay/Boon/ Xiao

Stored beam & occ. inc.


Wednesday, July 27, 2011



0000-0600

Setup 4NLSS lattice

Sajaev

Stored beam & inj.

0630-0800

Prepare for User beam (24 singlets-standard lattice)

OPS

Stored Beam & Injection