Machine Studies
Schedule for Run02-9, 2011
July 25th 0800 - July 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, July 25, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1130 |
Repair Johnson controls controller |
Wright |
No Beam Affects SR sectors 13-14 |
0930-1130 |
P.S. thermal scans Zone C |
P.S. Group |
No beam |
0930-1130 |
Remove blanking plate at flange RFTS118 |
Horan |
No Beam |
0930-1230 |
Investigate RF5 13.2kV disconnect dropout |
RF group |
No Beam |
1000-1100 |
Adjust upstream flange at BNL bellows |
Hoyt |
Access Zone D |
1000-1130 |
Phase shifter study for S37 LLRF crate |
Berenc |
No Beam |
1130-1230 |
Install phase shifter at RF2 |
Berenc |
No Beam |
1230-1530 |
Slow beam dump by resonance crossing (rf frequency) |
Chae/Yao |
Stored beam & inj. |
1530-1730 |
Make slow beam dump script |
Sajaev/Chae |
Stored beam & inj. |
1730-1900 |
SR requalification |
Fystro/ Schroeder |
Stored beam & injection |
1900-2400 |
P2 offsets measurement |
Xiao/Boon/ Harkay |
Stored beam & injection |
|
Tuesday, July 26, 2011 |
|
|
0000-0400 |
Coupling correction |
Sajaev |
Stored beam & inj. |
0400-1000 |
measure fast corrector's transfer function and open loop/close loop PSD in RTFB system |
Lenkszus/Xu |
Stored beam & injection |
1000-1100 |
4-ID-D Radiation Survey with White Beam |
Wyncott |
Stored beam |
1100-1300 |
measure booster chromaticity and BPM response (will be making large changes in frequency) |
Yao |
No SR beam |
1300-1700 |
Orbit Switch |
Xiao |
Stored beam & inj. |
1700-1800 |
Set-up P0 feedback with 24 singlets |
Yao |
Stored beam & inj. |
1800-2400 |
6BM steering studies for SCU0 (24 singlets, 100mA) |
Harkay/Boon/ Xiao |
Stored beam & occ. inc. |
|
Wednesday, July 27, 2011 |
|
|
0000-0600 |
Setup 4NLSS lattice |
Sajaev |
Stored beam & inj. |
0630-0800 |
Prepare for User beam (24 singlets-standard lattice) |
OPS |
Stored Beam & Injection |