Schedule for Run03-10, 2011

December 6th 0800 – December 7th 0800

Time

Descriptions

Studiers

SR Status


Tuesday, December 06, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/

OPS

Stored Beam & Injection

0930-1230

Move external monitoring from  converters SR 21AQ5 & 21BQ5 to S20AQ1 and S20A1Q3

Wang

No Beam

0930-1230

Hook up external clock monitoring at SR converter S15BH4

Fors

No Beam

0930-1030

Replace SCDU module for S19B:P5. IOCS19BPM will be rebooted

Keane

No beam

0930-1230

Thermal image SR Zones D & E

Puttkammer

No Beam

0930-1130

Reboot RF cavity IOCs

DiMonte

No beam

0930-1230

Troubleshoot S16AH4 and 12BH4

Puttkammer

No Beam

0945-1130

Replace S38 RF Cav 4 blowers

Morrison

No beam

1230-1300

Recover SR beam.

OPS

Stored Beam & Injection

1300-1400

Detune S40C3.

Harkay Horan Schroeder

Stored Beam & Injection

1400-1600

Investigate P0 feedback glitches.

Yao DiMonte

Stored Beam & Injection

1600-2000

Orbit switch.

Xiao

Stored Beam & Injection

2000-2300

Aperture scan tests for SCU0 commissioning.

Harkay Boon

Stored Beam & Injection

2300-2400

Injection optimization automation.

Sajaev

Stored Beam & Injection


Wednesday, December 07, 2011



0000-0200

Injection optimization automation (continued).

Sajaev

Stored Beam & Injection

0200-0700

4NLSS+RHB lattice setup.

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS