Schedule for Run03-2, 2011
October 11th 0800 - October 12th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, October 11, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930
|
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Reboot iocfe16 |
Smith |
No Beam |
0930-1000 |
Reboot siocsrscope |
DiMonte |
No Beam |
|
|
|
|
0930-1030 |
Test RF-5 PEM |
Yao, Soliday |
No Injection |
0930-1130 |
Test software changes in Linac |
Pietryla |
No Injection |
0930-1130 |
Back flush SR converters |
Puttkammer |
No Beam |
0930-1130 |
16-ID End-to-End test |
Budz |
No beam |
1100-1115 |
Reboot iocs15bpm |
Lenkszus |
No Beam |
1130-1200 |
Recovery from non-beam studies |
Ops |
Stored beam & injection |
1200-1600 |
CPU study |
Xiao/M. Smith |
Stored beam |
1200-1400 |
Develop K2 down mode files for both RF Guns |
Pasky |
Limited injection |
1600-1900 |
RTFB FF and freeze studies |
Emery/Xiao |
Stored beam & injection |
1900-2000 |
Test chromaticity script |
Yao/Shang |
Stored beam & inection |
2000-2400 |
Repeat instability with 24 singlet pattern and collect more info |
Yao/Harkay |
Stored beam & injection |
|
Wednesday, October 12, 2011 |
|
|
0000-0200 |
Storage-ring training |
Bogdan |
Stored beam & injection |
0400-0700 |
Measure the RTFeedback response matrix using the DSP85 response matrix measurement. |
Sereno/ Lenkszus |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |