Machine Studies
Schedule for Run03-3, 2011
October 18th 0800 - October 19th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, October 18, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0930-1000 |
Reboot all RTFB IOCs |
Lenkszus |
No beam |
0930-1000 |
Adjust RF3 phase loop offset |
Horan |
No Beam |
0930-1000 |
Check bunch cleaning FPGA box |
Yao |
No beam |
0930-1130 |
SR vibration measurements |
Preissner |
No Beam |
0930-1130 |
Back flush SR converters |
Puttkammer |
No Beam |
0930-1230 |
Test Linac PS software |
Hillman/Pietryla |
No Injection |
0930-1230 |
Replace RG1 Heater supply chopper |
Hillman |
No Injection |
1000-1200 |
Investigate 16ID PSS shutter fault |
Banks |
Access Zone B |
1230-1400 |
Linac RG1 study. |
Pasky |
No injection |
1400-1600 |
Collect NbBPM data. |
Bui |
Stored Beam & Injection |
1600 |
Fill 100mA, 24 singlets. |
OPS |
Stored Beam & Injection |
1600-1900 |
375 MeV injection. |
Sereno Yao |
No injection |
1600-1900 |
Steer beam at P5 bpms (parallel to injector studies). |
Sajaev |
Stored Beam |
1900-2100 |
Test new DSP85 response measurement. |
Sereno |
Stored Beam & Injection |
2100-2300 |
SR training. |
Mazzio |
Stored Beam & Injection |
2300-2400 |
RTFB freeze investigation. |
Emery Xiao |
Stored Beam & Injection |
|
Wednesday, October 19, 2011 |
|
|
0000-0100 |
RTFB freeze investigation (continued). |
Emery Xiao |
Stored Beam & Injection |
0100-0400 |
CPU test. |
Xiao |
Stored Beam & Injection |
0400-0700 |
Damping time with different chromaticity. |
Yao |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |