Machine Studies
Schedule for Run03-5, 2011
October 31st 0800 – November 2nd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, October 31, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0930-1000 |
Test shutters at 29ID |
McNamara |
No Beam |
0930-1030 |
Install vme module in iocbdg1 |
Laird |
No Beam |
0930-1130 |
Troubleshoot sectors 23 - 24 process water A-B PLC ethernet problem (pump 521 off) |
Putnam |
No beam |
0930-1030 |
SRRF waveguide switch |
Cours |
No Beam |
|
CANCELLED |
|
|
0930-1130 |
move the current measurement from S32B:Q1/S32:BQ1 to S31A:Q5/S31B:Q5 (double sector off) |
Puttkammer |
No beam |
0930-1230 |
Troubleshoot PAR RF-12 |
Smith |
Limited Injection |
1000-1100 |
Collect lead samples |
Bechtold, ESH |
Access Zone B |
1230-1300 |
Recover SR beam. |
OPS |
Stored Beam & Injection |
1300-1700 |
XBPM data collection script test. |
Decker Hahne Shang |
Stored Beam & Injection |
1700-2100 |
Characterize/collect BnBPM data. |
Bui Lill |
Stored Beam & Injection |
2100-2400 |
Set up hybrid lattice. |
Xiao |
Stored Beam & Injection |
|
Tuesday, November 01, 2011 |
|
|
0000-0100 |
Set up hybrid lattice (continued). |
Xiao |
Stored Beam & Injection |
0100-0500 |
DSP85 response measurements. |
Sereno |
Stored Beam & Injection |
0500-0700 |
PEM testing for PAR RF. |
Pasky |
Limited injection |
0700-0900 |
SR training. (last 1/2 hour no injection) |
Mazzio |
Stored Beam & Injection |
0830-1030 |
Replace a RF12 500W amplifier |
T. Smith |
No Injection |
0900-1100 |
check the Bergoz/filter/DBPLD interface labels in diagnostics cabinets around the ring |
Sun |
No impact |
0900-1100 |
SR RF PEM testing. Parallel to PAR RF. |
Soliday Horan Schroeder |
Stored Beam & Injection |
1030-1100 |
Check out PAR harmonic system |
Yao |
Limited Injection |
1100-1300 |
Measure SR damping time. |
Yao |
Stored Beam & Injection |
1300-1700 |
Orbit switch. |
Xiao |
Stored Beam & Injection |
1700-2300 |
Tune up booster injection with 375MeV. |
Yao Sereno |
Limited injection |
1700-2100 |
CPU measurements. Parallel to booster injection. |
Xiao |
Stored beam |
2300-2400 |
Test ID steering to center of BPLDs. |
Sajaev |
Stored Beam & Injection |
|
Wednesday, November 02, 2011 |
|
|
0000-0100 |
Test ID steering (continued). |
Sajaev |
Stored Beam & Injection |
0100-0400 |
Continue P5 steering. |
Sajaev |
Stored Beam & Injection |
0400-0700 |
Continue 4NLSS lattice. |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |