Machine Studies
Draft Schedule for Run03-9, 2011
November 29th 0800 – November 30th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, November 29, 2011 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving DSPs |
PS group |
No Injection |
0930-1130 |
Vibration measurements w/ DI pumps off |
Pressner |
No Beam (affects SR sectors 10-13) |
0930-1200 |
Verify RF test stand waveguide air pressure (All Bldg. 420 systems off) |
Horan |
No Beam |
0930-1200 |
Move external monitoring from converters S23AQ1 and S231Q3 to SR 21AQ5 & 21BQ5 |
Wang |
No Beam |
0930-1200 |
Troubleshoot B:IK |
Donley |
No Injection |
0930-1200 |
Hook up external clock monitoring at SR converter S21AV3 |
Fors |
No Beam |
1000-1100 |
Switch injectors back to 325MeV operation |
OPS |
No beam |
1100-1300 |
SR qualification testing / training |
Bogdan/ Schroeder |
No other studies 1200-1300 |
1300-1400 |
Test RF Cavity IOC reboots with beam |
DiMonte |
Stored beam & injection |
1400-1800 |
CPU studies with 4-ID beamline (shutters open) |
Xiao/Moog/ 4-ID |
Stored beam & injection |
1800-2200 |
Orbit switch to RHB |
Xiao |
Stored beam & injection |
2200--2400 |
Scan P0 feedback delays (remote study) |
Yao |
Stored beam & inj. |
|
Wednesday, November 30, 2011 |
|
|
0000-0630 |
4NLSS lattice set-up |
Xiao |
Stored beam & injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |