Machine Studies

Schedule for Run01-10, 2012

April 3rd 0800 – April 4th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, April 03, 2012



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0800-0810

Observe (BM shutter behavior

Forrestal

Stored Beam & Injection

0810-0900

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0900-0930

Reboot interleaving PS DSPs

PS Group

No Injection

0900-0930

Restart Metasys gateway

Smith

Stored Beam & Injection

0900-1000

Correct Booster RF timing changes

Di Monte

No Injection

0900-1000

Replace XMS101 board in iocid19

Pietryla

No Beam

0900-1100

Linac requalification

Weyer

Limited Injection

0900-1100

Reconnect and test 29ID BIV

McNamara

No Beam

0900-1100

Investigate B:IK drop outs

Donley

Limited Injection

0900-1100

Move SR Sextupole test stand to S20

Wang

No Beam

0900-1100

Test SR converter start up scripts

Fors

No Beam

0900-1100

Spot-knock RF2

RF Group

No beam

0900-1100

reset/replace GPS Time & Frequency Receiver

RF Group

No beam

1100-1200

get some FPGA data for hybrid mode.

C. Wang/Yao

Stored beam & inj.

1200-1300

Test a new ramp timing setting

Yao/Lenkszus

Booster injection

1300-1700

SR injection with low-emittance booster study.

Yao/Sajaev

Stored beam & injection

1700-1900

multi-bunch accumulation limit study.

Yao

Stored beam & injection

1900-2300

xbpm studies at 29-ID, shutter permit needed, top-up desirable

Decker/Yang

Stored beam & injection

2300-2400

tilt studies using phase detctor and rf button bpms

Sereno/Lill

Stored beam & injection


Wednesday, April 04, 2012



0000-0300

Tilt studies using phase detctor and rf button bpms (continued)

Sereno/Lill

Stored beam & injection

0300-0700

Sextpole offset measurement (improving the tools)

Xiao

Stored beam & inj.

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection