Machine Studies

Draft Schedule for Run01-2, 2012

February 8th 0800 - February 9th 0800



Time

Descriptions

Studiers

SR Status


Tuesday, February 07, 2012



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam & Injection

0930-1000

Reboot interleaving PS DSPs

Fors

No Injection

0930-1000

Reboot ioclnds and restart metasys

Smith

Stored Beam & Injection

0930-1030

Swap out Bergoz receiver at 16CP0

Erwin

No Beam

0930-1030

Replace L5 BUG

Pietryla

No Beam

0930-1130

Troubleshoot B:IK readback problems

Donley

No Injection

0930-1130

Investigate B:SD PS trips

Puttkammer

No Injection

0930-1130

Fix QD & QF scaling error

Yao/Shang

No injection

0930-1130

Repair DI water flow meters

Wright

No Beam

0930-1130

Replace the L5 power supply and perform necessary validations

Horan

No Injection

1000-1100

Check thermocouples at S37

Hoyt

Access Zone F

1000-1100

Replace rotary encoder at S29DS

Grimmer

Access Zone E

1100-1130

Recover SR systems

OPs

Stored Beam & Injection

1130-1330

Tuning the PID loop for Sector 33-34 vacuum chambers

Putnam/Erwin/Pasky

Stored beam

1130-1430

run booster with increased I-ramp delays

Yao/Lenkzsus/ Sereno

Limited injection

1430-1630

optimize P0 feedback x-plane settings and investigate abnormal tune response

Yao

Stored beam & inj.

1630-1830

Xbpm calibration 100mA top-up

Hahne

Stored beam & inj.

1830-2230

Continue with the xbpm studies at 29-ID - 100mA top-up (Shutters open)

Decker

Stored beam & inj.

2230-2400

New BPM offset measurement

Xiao

Stored beam & injection


Wednesday, February 08, 2012



0000-0300

New BPM offset measurement (cont)

Xiao

Stored beam & inj.

0300-0700

4NLSS lattice studies (continued)

Sajaev

Stored beam & inj.

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection