Draft Schedule for Run01-2, 2012
February 8th 0800 - February 9th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 07, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving PS DSPs |
Fors |
No Injection |
0930-1000 |
Reboot ioclnds and restart metasys |
Smith |
Stored Beam & Injection |
0930-1030 |
Swap out Bergoz receiver at 16CP0 |
Erwin |
No Beam |
0930-1030 |
Replace L5 BUG |
Pietryla |
No Beam |
0930-1130 |
Troubleshoot B:IK readback problems |
Donley |
No Injection |
0930-1130 |
Investigate B:SD PS trips |
Puttkammer |
No Injection |
0930-1130 |
Fix QD & QF scaling error |
Yao/Shang |
No injection |
0930-1130 |
Repair DI water flow meters |
Wright |
No Beam |
0930-1130 |
Replace the L5 power supply and perform necessary validations |
Horan |
No Injection |
1000-1100 |
Check thermocouples at S37 |
Hoyt |
Access Zone F |
1000-1100 |
Replace rotary encoder at S29DS |
Grimmer |
Access Zone E |
1100-1130 |
Recover SR systems |
OPs |
Stored Beam & Injection |
1130-1330 |
Tuning the PID loop for Sector 33-34 vacuum chambers |
Putnam/Erwin/Pasky |
Stored beam |
1130-1430 |
run booster with increased I-ramp delays |
Yao/Lenkzsus/ Sereno |
Limited injection |
1430-1630 |
optimize P0 feedback x-plane settings and investigate abnormal tune response |
Yao |
Stored beam & inj. |
1630-1830 |
Xbpm calibration 100mA top-up |
Hahne |
Stored beam & inj. |
1830-2230 |
Continue with the xbpm studies at 29-ID - 100mA top-up (Shutters open) |
Decker |
Stored beam & inj. |
2230-2400 |
New BPM offset measurement |
Xiao |
Stored beam & injection |
|
Wednesday, February 08, 2012 |
|
|
0000-0300 |
New BPM offset measurement (cont) |
Xiao |
Stored beam & inj. |
0300-0700 |
4NLSS lattice studies (continued) |
Sajaev |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |