Draft Schedule for Run01-3, 2012
February 14th 0800 - February 15th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 14, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0810-0900 |
Test BTS:APH3 |
Erwin |
No impact |
0900-1100 |
Investigate S15B:H4 blown output filter fuse |
Puttkammer |
No Beam |
0900-1100 |
Move current monitoring from S17 to S16 |
Wang |
No Beam |
0900-1100 |
Insert blanking plate for 420 RF test stand |
RF Group |
No Beam |
0900-1100 |
Investigate S32A:Q5 glitches |
Fors |
No Beam |
0900-1100 |
Linac beam & PEM tool studies |
Pasky/Soliday |
Limited injection |
0930-1030 |
S37 cooling jacket/ thermocouple work |
Hoyt |
Access Zone F |
1100-1300 |
test PAR harmonic amplifier tube #1. Needs PAR injection. |
T. Smith/Yao/ Harkay |
Limited injection |
1100-1300 |
Adjusting PID loop on vacuum chamber water S19-20, S21-22, S33-34 |
Putnam/Erwin/Pasky |
Stored beam |
1300-1500 |
booster on-momemtum test. Requires change to rf frequency. Needs booster injection |
Yao/Sereno |
No SR beam |
1500-1700 |
investigate SR sensitivity to tune measurement problem. Need to adjust chromaticity |
Yao |
Stored beam & inj. |
1700-2100 |
aperture scan studies for SCU0. |
Harkay/Boon |
Stored beam & inj. |
2100-2400 |
29-ID xbpm studies, 24 singlet top-up, 102mA, shutter permit needed |
Decker/Yang |
Stored beam & Inj. |
|
Wednesday, February 15, 2012 |
|
|
0000-0100 |
29-ID xbpm studies, 24 singlet top-up, 102mA, shutter permit needed (continued) |
Decker/Yang |
Stored beam & Inj. |
0100-0400 |
Setup/verify hybrid operation |
Sajaev |
Stored beam & inj. |
0400-0700 |
4NLSS lattice setup |
Sajaev |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |