Machine Studies
Schedule for Run01-4, 2012
February 21st 0800 - February 22nd 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, February 21, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-1000 |
Switch from pump 518 & 517 (affects SR S19&20 -- p.s. should be set to zero) |
Theres |
No beam |
0900-1100 |
SR RF PEM testing |
Horan/Soliday/Schroeder |
No Beam |
0900-1100 |
Move external monitoring from S16 to S15 |
Puttkammer |
No Beam |
1000-1200 |
measure externally the output current of S16C:BM p.s. |
Puttkammer |
No Beam |
0900-1100 |
Linac studies |
Pasky |
Limited injection |
0900-1200 |
Investigate S32A:Q5 read back |
Fors |
No Beam |
0900-1300 |
Troubleshoot PAR RF1 amp #1 |
RF Group |
Limited Injection |
1200-1400 |
Tune PID loops -- Sectors to be determined |
Putnam/Erwin/Pasky |
Stored beam |
1300-1400 |
test PAR harmonic tube#1 with beam after RF group study |
Yao Harkay |
Limited injection |
1400-1600 |
setup P0 feedback for hybrids fill. |
Yao |
Stored beam & inj. |
1600-1930 |
ID-29 Xray BPM studies with 102mA top-up (shutter permit needed) |
Decker/Yang |
Stored beam & inj. |
1930-2300 |
P3/P4 Offset Measurements |
Xiao |
Stored beam & inj. |
2300-2400 |
complete hybrid lattice setup |
Sajaev |
Stored beam & inj. |
|
Wednesday, February 22, 2012 |
|
|
0000-0100 |
complete hybrid lattice setup (continued) |
Sajaev |
Stored beam & inj. |
0100-0300 |
injection optimization tool development |
Sajaev |
Stored beam & inj. |
0300-0700 |
4NLSS+RHB lattice setup |
Sajaev |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |