Machine Studies
Schedule for Run01-8, 2012
March 20th 0800 – March 21st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, March 20, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0900 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0900-0930 |
Reboot interleaving PS DSPs |
PS Group |
No Injection |
0900-1100 |
Check RF5 PLC analog cards |
RF group |
No Injection |
0900-1200 |
Move external monitoring |
Wang |
No Beam |
0900-1200 |
Inspect and adjust SR fast correctors S12 & 18 |
Puttkammer |
No Beam |
0900-1200 |
RF3 measurements |
RF Group |
No Beam |
0930-1030 |
Repair 30-ID encoders |
Merritt |
Zone E Access |
1200-1300 |
Tune slope measurement in 324 singlets |
Harkay |
Stored beam & injection |
1300-1600 |
Sextupole offset measurements |
Xiao |
Stored beam & inj. |
1600-2000 |
Xbpm studies at 29-ID (shutter permit needed) |
Decker/Yang |
Stored beam & inj. |
2000-2400 |
Beam tilt studies |
Sereno/Lill |
Stored beam & inj. |
|
Wednesday, March 21, 2012 |
|
|
0000-0400 |
Continue 4NLSS+SPX lattice setup
|
Sajaev |
Stored beam & inj. |
0400-0700 |
Continue 4NLSS+RHB lattice setup |
Sajaev |
Stored beam & inj. |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |