Draft Schedule for Run02-1, 2012
May 23rd 0800 – May 30th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Wednesday, May 23, 2012 |
|
|
0800-0945 |
Continue Rf conditioning |
OPS |
Stored beam & inj. |
0945-1200 |
Access to install new cooling clamps and turn on water to all installed clamps on S6 chamber |
MOM group |
Stored beam & inj |
1200-2000 |
RF conditioning with beam |
OPS |
Stored beam & inj. |
1400-1700 |
Preliminary BPM system checkout (parasitic only) |
Decker |
Stored beam & inj. |
|
canceled due to delay in conditioning |
|
|
|
canceled due to delay in conditioning |
|
|
2000-2400 |
BPLD validation. |
Bui |
Stored Beam & Injection |
|
Thursday, May 24, 2012 |
|
|
0000-0800 |
24 singlets initial lattice setup. |
Sajaev |
Stored Beam & Injection |
0800-1200 |
PSS shutter tests |
SI Group |
No Beam |
0800-0815 |
Archive kicker waveforms |
OPS |
No beam |
0800-1200 |
Switch pump 528 over to 527 for vibration testing. (PS to zero) |
Theres |
No beam |
0815-1200 |
Install instrumentation to monitor IK1 & IK3 |
Hillman |
No beam |
0800-0900 |
RF waveguide switch to RF1&RF2 & MPS validation |
RF Group/M. Smith |
No beam |
0900-1200 |
PSS end-to-end tests for 23 & 1 |
SI Group |
No Beam |
1200-1800 |
Orbit recovery. |
Xiao |
Stored Beam & Injection |
1800-2400 |
Intermediate BPM system checkout. |
Decker Hahne |
Stored Beam & Injection |
|
Friday, May 25, 2012 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0800-0830 |
fix/test a cable/fiber problem in SR sector 13 cabinet 2 correctors |
Puttkammer |
No beam |
|
|
|
|
|
|
|
|
|
|
|
|
0000-0800 |
Investigate injection/lifetime issues |
Sajaev/Emery/Decker |
Stored beam & injection |
0800-2400 |
Access to investigate injection, replacement of S6 ID chamber |
Multiple groups |
No beam |
|
Saturday, May 26, 2012 |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
0000-2400 |
S6 bake-out (bake-out started at 12:45) |
MOM group |
No beam |
|
Sunday, May 27, 2012 |
|
|
0000-2400 |
S6 bake-out and post bake-out work |
Multiple groups |
No SR beam |
0800-1200 |
Booster ORM measurements. |
Yao |
Injector beam |
1200-1600 |
375 MeV injector setup |
|
Injector beam |
|
|
|
|
|
|
|
|
|
|
|
|
|
Monday, May 28, 2012 |
|
|
|
|
|
|
0300-0700 |
Orbit recovery |
Xiao |
Stored beam & injection |
0700-1300 |
CPU checkout 1. |
Xiao |
Stored Beam & Injection |
1300-1700 |
BPM studies |
Decker |
Stored Beam & Injection |
|
|
|
|
1700-2400 |
Top-up test run |
OPS |
Stored beam & injection |
|
Tuesday, May 29, 2012 |
|
|
0000-0400 |
Injection studies |
Sajaev |
Stored Beam & Injection |
0400-0800 |
Coupling minimization using ORM |
Sajaev |
Stored Beam & Injection |
0800-1000 |
S35BM pinhole setup for user run. |
Yang |
Stored Beam & Injection |
1000-1200 |
S35ID/S36AM bunch purity monitor setup for user run. |
Yang |
Stored Beam & Injection |
|
|
|
|
1200-1600 |
Final BPM system checkout. |
Decker Hahne |
Stored Beam & Injection |
1600-2400 |
CPU check #2 |
Xiao |
Stored Beam & Injection |
|
Wednesday, May 30, 2012 |
|
|
0000-0300 |
Hybrid lattice setup. |
Sajaev |
Stored Beam & Injection |
0300-0600 |
Final lattice and injection setup. |
Sajaev |
Stored Beam & Injection |
0600-0800 |
Prepare for user Operations (24 singlets – Top-Up) |
Ops |
Stored Beam & Injection |