Machine Studies
Draft Schedule for Run02-10, 2012
July 31st 0800 – August 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, July 31, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0845 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0845-0900 |
SI group test cycling shutters on 10-BM |
SI group |
Stored beam |
0900-1100 |
Vibration studies w/ shutters open |
OPS/FMS |
Stored Beam & Injection |
1100-1200 |
Pull cable from 38-01 to 38-04 |
Erwin/Wright |
No Impact |
1100-1300 |
Investigate S40A:Q5 readback |
PS Group |
No Beam |
1100-1300 |
Thermal image Zone A converters |
Puttkammer |
No Beam |
1100-1300 |
Move external monitoring equipment |
Wang |
No Beam |
1130-1200 |
Switch from standby pump to pump 906 (RF3 off) |
Wright |
No beam |
1130-1330 |
Replace encoders in S24 & 26 |
Merritt |
Authorized Access Zone D |
1130-1330 |
Investigate/repair 26ID shutter |
Banks |
Authorized Access Zone D |
1330-1400 |
Recover SR systems |
OPS |
Stored Beam & Injection |
1400-1600 |
Teng student studies |
Ops, others |
Stored Beam & Injection |
1600-2000 |
setup and optimize booster low-emittance lattice for 375 MeV. Booster injection only. |
Yao |
Booster beam (no SR injection) |
1730-1930 |
Remote access demo at 17-ID (shutter permit needed) |
17-ID |
Stored beam |
2000-2100 |
acquire booster beam current waveform with RF drive off |
Yao |
Booster beam (no SR injection) |
2100-2300 |
scan rf frequency with stored beam and measure noise spectrum. 24-singlet fill. Sweep SR rf frequency by up to +-2 kHz |
Yao |
Stored beam & injection |
2300-2400 |
IEX studies |
Xiao |
Stored beam & injection |
|
Wednesday, August 1, 2012 |
|
|
0000-0500 |
IEX studies (continued) |
Xiao |
Stored beam & injection |
0500-0700 |
OPEN |
|
|
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |