Machine Studies
Schedule for Run02-3, 2012
June 12th 0800 - June 13th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, June 12, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1130 |
Test IEX scripts |
Xiao |
No Beam |
0930-1200 |
Inspect /replace cooling fans for canted PS |
Puttkammer |
No Beam |
0930-1130 |
Test tuning of harmonic RF tube #1. |
Yao Horan |
PAR |
1200-1230 |
Restore SR systems |
OPS |
Stored Beam & Injection |
1230-1400 |
Test iocs33fb upgrade. |
Xu Lenskzus |
Stored Beam & Injection |
1400-1800 |
Xbpm data collection. |
Hahne |
Stored Beam & Injection |
1400-1600 |
Water PID loops adjustment (parallel to xbpms). |
Erwin Putnam |
Stored Beam & Injection |
1600-1800 |
Take FPGA bpm data for rtfb simulations (parallel to xbpms). |
Sereno |
Stored Beam & Injection |
1800-2400 |
IEX studies. |
Xiao |
Stored Beam & Injection |
|
Wednesday, June 13, 2012 |
|
|
0000-0300 |
Tune injectors for 375 MeV injection |
Yao Sereno Sajaev |
Stored Beam & Injection |
0300-0700 |
Single bunch accumulation limit study. |
Yao Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |