Machine Pre-Studies
Schedule for Run03-1, 2012
Sep 21st 0800 – Oct. 1st 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Fri, Sep 21, 2012 (Pre-Studies) |
|
|
0800-1200 |
MPS validations, final checkout |
Smith |
|
1200-1600 |
Continue rf conditioning |
RF group |
|
1400-1630 |
Establish injection. |
Sajaev |
Stored Beam & Injection |
1630-1930 |
Aperture scan, SCU0 test chamber, 1-2 mA (P1s) |
Borland Emery Harkay Sajaev Zholents Boon |
Stored Beam & Injection |
1930-2100 |
Beam steering setup; preliminary beam-based alignment, SCU0 test chamber , < 25 mA |
Borland Emery Harkay Sajaev Zholents Boon |
Stored Beam & Injection |
2130-2400 |
Accumulate 100 mA in 324 bunches; fill-on-fill. Measure x,y tunes at intervals of 5 mA. No P0 FB. |
OPS |
Stored Beam & Injection |
|
Sat, Sep 22, 2012 (Pre-studies) |
|
|
0000-1100 |
Accumulate 100 mA in 324 bunches (cont). |
OPS |
Stored Beam & Injection |
1100-1700 |
FPGA BPM setup, < 5 mA |
Sereno |
Stored Beam & Injection |
1700-2130 |
Accumulate 100 mA in 324 bunches. Measure x,y tunes at intervals of 5 mA (cont from 1100) |
OPS |
Stored Beam & Injection |
1700-2200 |
Beam-based alignment, SCU0 test chamber, <80 mA |
Borland Harkay Boon |
Stored Beam & Injection |
2200-2400 |
Dump beam, measure cooldown. |
Borland Harkay Boon |
Stored Beam & Injection |
|
Sun, Sep 23, 2012 (Pre-studies) |
|
|
0000-2400 |
Rf conditioning, 115 mA, 24 bunches. Measure x,y tunes at intervals of 5 mA. No P0 FB. |
OPS |
Stored Beam & Injection |
1800-2200 |
Beam-based alignment (parasitic to 324-bunch accum) |
Harkay Xiao Boon |
Stored Beam |
|
Mon, Sep 24, 2012 (Pre-studies) |
|
|
|
Continuation of rf conditioning if needed |
|
Stored Beam & Injection |
0830-0900 |
Meeting: studies status |
A1100 |
|
|
Initial set-up of Pinhole camera (more than 40ma – can be parasitic to RF conditioning) |
Yang |
Stored Beam & Injection |
|
P0FB system setup (after conditioning) |
Yao |
Stored Beam & Injection |
|
Tuesday, Sep 25, 2012 |
|
|
0000-0800 |
Pre-studies (OPEN) |
|
|
0800-1200 |
BPLD validation. |
Bui |
Stored Beam & Injection |
1200-1600 |
X-ray BPM checkout. |
Hahne |
Stored Beam & Injection |
1600-2200 |
Orbit Recovery + switch to RHB |
Xiao |
Stored beam & injection |
2200-2400 |
Install P1/P5 offsets |
Xiao |
Stored beam & injection |
|
Wednesday, Sep 26, 2012 |
|
|
0000-0200 |
Install P1/P5 offsets (continued) |
Xiao |
Stored Beam & Injection |
0200-0700 |
OPEN |
|
|
0700-0900 |
cancelled due to IOC work |
Hahne |
Stored Beam & injection |
0900-1300 |
Orbit cleanup |
Sajaev |
Stored Beam & Injection |
1300-1700 |
RHB lattice correction |
Sajaev |
Stored Beam & Injection |
1700-2100 |
Set up S35 Pinhole camera |
Yang |
Stored Beam |
1700-1900 |
Scan PAR kicker timing and optimize par beam |
Yao |
Occasional injection |
2100-2400 |
CPU Checkout 1 |
Xiao |
Stored Beam |
2100-2400 |
Set up the 150 MeV lattice to the BB-Dump |
Sereno/Pasky |
Occ. injection possible |
|
Thursday, Sep 27, 2012 |
|
|
0000-0300 |
CPU Checkout 1 (continued) |
Xiao |
Stored Beam |
0000-0300 |
Set up the 150 MeV lattice to the BB-Dump |
Sereno/Pasky |
Occ. injection possible |
0300-0800 |
OPEN |
|
|
0800-1200 |
PSS shutter tests |
SI Group |
No beam |
0800-0900 |
Reboot lic iocs |
Pietryla |
No injection |
0900-1100 |
Test RF conditioning sequence |
Pietryla/Pasky |
No injection |
0800-1200 |
test booster ramp current ADC card |
Yao, Shang, Wang, Xu |
No injection |
0800-1000 |
Investigate BEK Kicker power supply faulty digital meter |
Hillman |
No injection |
0800-1000 |
investigate S16AQ5 unstable read backs |
Puttkammer |
No SR beam |
0800-1000 |
Perform air temperature monitoring in SR Sector 25 converter cabinet 2 |
Sprau |
No SR beam |
0830-0900 |
HP survey at Zone E/F gate |
Vacca |
Access Zone E |
0830-0900 |
Check BLM in S33 |
Brill/Dooling |
Access Zone E |
0900-1100 |
Troubleshoot 13-ID rotary encoder |
Grimmer/ Merritt |
Access Zone B |
0930-1130 |
Replace S37 Cav 4 US & CAV 3 DS IR thermometers |
Morrison |
Access Zone F |
0930-1130 |
Investigate low flow at S35BM FM2 |
Theres |
Access Zone F, Possible access Zone E |
0930-1130 |
Repair/replace S39:IK2 blower |
Morrison |
Access Zone F |
1130-1200 |
Recover SR |
OPS |
Stored beam & inj. |
1200-1500 |
Chromaticity /dispersion measurement of booster low-emittance lattice |
Yao |
No SR beam |
1500-2100 |
IEX prepare 1 |
Xiao |
Stored beam & injection |
2100-2400 |
FPGA data collection |
C. Wang |
Stored beam & injection |
|
Friday, Sep 28, 2012 |
|
|
0000-0200 |
FPGA data collection (continued) |
C. Wang |
Stored beam & injection |
0200-0600 |
Injection optimization program debugging |
Sajaev |
Stored beam & injection |
0600-0900 |
check and retune PID loops on Water skids 2,12,14, and 40 |
Putnam |
Stored beam |
0700-0900 |
Continue XBPM studies |
Hahne |
Stored beam& inj. |
0900-1300 |
24 singlet lattice set-up |
Sajaev |
Stored Beam & Injection |
1300-1900 |
CPU Checkout 2 |
Xiao |
Stored Beam & Injection |
1900-2400 |
FPGA data collection (continued) |
C. Wang |
Stored beam & injection |
|
Saturday, Sep 29, 2012 |
|
|
0000-0800 |
Switch to RG2 |
OPS |
Limited injection |
0800-1200 |
Bunch purity measurement set-up |
Yang |
Stored Beam & Injection |
1200-1800 |
IEX prepare 2 |
Xiao |
Stored Beam & Injection |
1800-2400 |
Top-up Verification |
OPS |
Stored Beam & Injection |
|
Sunday, Sep 30, 2012 |
|
|
0000-0600 |
Top-up Verification |
OPS |
Stored Beam & Injection |
0600-0700 |
OPEN |
|
|
0700-0800 |
Set-up for supplemental shielding tests |
Borland/ Dooling |
No injection |
0800-1600 |
perform tests of the new supplemental shielding installed in the LTP and Booster |
Borland/ Dooling/Vacca |
No injection |
1600-2400 |
Switch to RG1 |
OPS |
Limited injection |
|
Monday, Oct 1, 2012 |
|
|
0000-0900 |
aperture scans in 6ID and steering in 6BM |
Harkay/Boon |
Stored Beam & Injection |
0900-1700 |
Final BPM checkout |
Decker |
Stored Beam & Injection |
1700-2100 |
Final setup of pinhole camera |
Yang |
Stored Beam & Injection |
2100-2400 |
Impedance test lattice setup (hybrid-like fill) |
Sajaev |
Stored Beam & Injection |
|
Tuesday, Oct 2, 2012 |
|
|
0000-0300 |
Impedance test lattice setup (hybrid-like fill) (continued) |
Sajaev |
Stored Beam & Injection |
0300-0600 |
Final lattice and injection setup. |
Sajaev |
Stored Beam & Injection |
0600-0800 |
Prepare for user Operations (24 singlets RHB – Top-Up) |
Ops |
Stored Beam & Injection |