Machine Studies

Draft Schedule for Run03-5, 2012

October 29th 0800 – October 31 st 0800

Time

Descriptions

Studiers

SR Status


Monday, October 29, 2012



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/OPS

Stored Beam & Injection

0930-1330

Troubleshoot problem with AGC loop for RF3/S36/S37

RF Group

No Beam

0930-1130

Linac studies -- water station PID loop tuning automation

Pasky/ Sereno

No injection

0930-1330

Waveguide switches to verify RF-1 phase loop and back

RF Group

No Beam

0930-1030

AHU work for S37/38

Erwin/FMS

No Beam

0930-1130

Replace filters on S5&6 vacuum chamber cooling water skid

Swetin

No beam

0930-1230

Testing IEX control

Xiao

No beam

0930-1330

Replace the ECF diode stack in BES2 Septum power supply

Deriy

No Beam

0930-1330

Move the external current monitors on SR Sextupoles in Zone E

Wang

No Beam

0930-1330

Investigate glitchy read-backs in S40AQ5 converters and script testing

Fors

No Beam

0930-1330

Upgrade the Canted Corrector cooling fans in sector 12 and 34

Puttkammer

No Beam

0930-1330

Investigate why L1:QM2 power supply won’t turn on remotely

Donkers

Limited Injection

0930-1130

Conduct B&K Modulator Module measurements at RF2, RF3 and RF4

Berenc

No beam

0930-1430

Replace valve & actuator in S13/14 Vacuum chamber water skid (water skid shutdown)

Putnam

No beam

1000-1030

Switch process water pump for S35/36

Wright

No Beam

1100-1630

Booster main ramp ADC test (Limited injection from 14:30)

Yao/Wang/ S. Xu/Shang

Limited Injection

1330-1430

PAR requealification

Pasky/ACO

Limited injection

1430-1630

Tune PID loop for S13/14 vacuum chamber water skid

Putnam

Stored beam

1430-1630

Set-up pinhole camera

Yang

Stored beam

1630-1830

Set-up P0 feedback for hybrid

Yao

Stored beam & injection

1830-2400

SCU0 thermal studies with 6BM steering

Harkay/Boon

Stored bean & injection


Tuesday, October 30, 2012



0000-0400

Orbit recovery

Xiao

Stored beam & injection

0400-0800

CPU studies

Xiao

Stored beam & inj.

0800-1000

test a few storage ring feedback iocs' upgrade with beam

S. Xu, Lenkszus

Stored beam & injection

1000-1030

Set-up for 130mA study

OPS/Schroeder

Stored beam & inj.

1030-1430

130mA study, 24 singlets

Harkay/ Schroeder

Stored beam & inj.

1030-1430

record pressure and BLM data during the 130 mA study.

Dooling

Stored beam & inj.

1430-1500

Recover from 130mA study

OPS/Schroeder

Stored beam & inj.

1500-1600

test swtich chromaticity app

Yao/Shang

Stored beam & inj.

1600-1800

Single bunch accumulation limi

Yao

Stored beam & inj.

1800-2000

FPGA BPM based optics correction. Low current single bunch with occasional injection

C. Wang

Stored beam & inj.

2000-2400

IEX studies

Xiao

Stored beam & injection


Wednesday, October 31, 2012



0000-0100

IEX studies

Xiao

Stored beam & injection

0100-0700

Continue impedance lattice studies

Sajaev

Stored Beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection