Machine Studies
Schedule for Run03-6, 2012
November 6th 0800 – November 7tht 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, November 6, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder/OPS |
Stored Beam & Injection |
0810-0930 |
measure S38 bpm noise with hybrid top-up (parasitic) |
Sereno |
Stored beam & injection |
0930-1000 |
Reboot interleaving DSPs |
PS Group |
Limited Injection |
0930-1030 |
Test repaired Pentek 4283 DSP card in iocs1fb |
Lenkszus |
No Beam |
0930-1100 |
Work on control valve actuator for S13-14 |
Putnam |
No Beam |
0930-1000 |
PSS end to end test 29ID |
McNamara |
A-E in controlled access |
0930-1130 |
Replace chilled water filters on vacuum chamber cooling water skids SRVC-04, 10, 12, 28, 36 |
Swetin |
No impact |
0930-1130 |
Move external monitoring equipment in Zone E |
J. Wang |
No Beam |
0930-1230 |
test the IEX control software |
Xiao/M. Smith |
No beam |
0930-1130 |
Investigate Dac clamp in S8A:H1 |
Fors |
No Beam |
0930-1130 |
Connect L1 Quads Gespac fiber |
Hillman |
Limited Injection |
0930-1130 |
Replace B:IS HVPS |
Deriy |
No Injection |
0930-1130 |
Replace 20MHz source/distribution chassis in Linac |
Horan |
No Injection |
0930-1330 |
Perform heater emission curve on RF3 |
RF Group |
No Beam |
0930-1130 |
Test Booster ramp new ADC |
Yao, Xu, Laird |
No Injection |
1300-1330 |
measure the beam size at LTP:FL1 |
Sereno |
No injection |
1330-1400 |
test button to disable 2 Hz triggering of FPGA bpms. |
Sereno |
No injection |
1400-1600 |
Tune PID loop with beam (S13-14 Vacuum Skid Water) |
Putnam |
Stored beam & occ. inj. |
1400-1600 |
Continue to measure S38 bpm noise with hybrid top-up (parasitic) |
Sereno |
Stored beam & injection |
1600-1800 |
collect noise response of beam with P0 feedback on (hybrid fill) |
Yao |
Stored beam & inj. |
1800-2400 |
IEX studies |
Xiao |
Stored beam & inj |
|
Wednesday, November 7, 2012 |
|
|
0000-0300 |
Optics corrections |
C. Wang |
Stored beam & injection |
0300-0700 |
Impedance lattice studies |
Sajaev |
Stored beam & injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |