Draft Schedule for Run03-9, 2012

November 27th 0800 – November 28th 0800

Time

Descriptions

Studiers

SR Status


Tuesday, November 27, 2011



0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder/OPS

Stored Beam & Injection

0930-1000

Reboot interleaving DSPs

PS group

No Injection

0930-0940

Condition IEX magnets

OPS/Schroeder

No beam

0930-1200

Replace RF cavity blowers S36

Morrison

Zone F Access

0930-1030

Relocate diagnostic FPGA iocbunchpure2

Shoaf

No Beam

0930-1030

Install virtual BPM database in iocsbpmdp

Lenkszus

No Beam

0930-1130

Investigate B:IS issues

Deriy

No Beam

0930-1230

Investigate bit-bus errors in S25 & S36

Puttkammer

No Beam

0930-1230

Measure ground fault currents S2:3

Sprau

No Beam

1200-1500

Test modulator module at RF4

RF Group

No Beam

1230-1430

Move external monitors in Zone F

J. Wang

No Beam

1430-1500

Recover all systems in preparation for storing beam at 15:00

OPS

Stored beam & injection

1500-1800

test booster ramp new ADC card, requires SR BM and RF running normal level

Yao/J. Wang/ Shang/S. Xu/ Laird

No injection

1800-2200

bunch length vs bunch current using the streak camera. Single bunch 0-20 mA

Harkay/Boon/Yang

Stored Beam & injection

2200-2400

CPU studies

Xiao

Stored beam & injection


Wednesday, November 28, 2011



2200-0300

CPU studies (continued)

Xiao

Stored beam & injection

0300-0700

IEX readiness

OPS/Xiao

Stored beam & injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection