Machine Studies
Schedule for Run01-12, 2013
April 16th 0800 – April 17th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, April 16, 2013 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0810-0930 |
Test of S36 bpms (parallel to gap scans). |
Sereno |
Stored Beam & Injection |
0930-1030 |
RF waveguide switch from RF2 to RF3 |
RF Group |
No Beam |
0930-1030 |
Switch pump P-SR-18A (PS on either side of S18 off) |
Swetin |
No Beam |
0930-1130 |
Reboot FPGA bpm iocs |
Pietryla |
No Beam |
0930-1130 |
Remove actuator off water skid 14 |
Erwin/Swetin |
No Beam |
0930-1200 |
Thermal scan Zone D/E PS |
Puttkammer |
No Beam |
0930-1330 |
Investigate intermittent performance of RF-5 |
RF Group |
Limited Injection |
1200-1400 |
FPGA data aquisition work (parallel to RF-5 work). |
Wang Shang |
Stored Beam & Injection |
1400-1600 |
Measure injector bunch purity. |
Yao Yang |
Stored Beam & Injection |
1600-2100 |
Punch down A:HV4 correctors and install new BPM offsets (in 24 singlets mode). |
Xiao |
Stored Beam & Injection |
1600-2100 |
Injector training (parallel, when compatible with punching down correctors). |
Obasohan |
Limited Injection |
2100-2400 |
Measure accumulation limit for different chromaticities. |
Sajaev |
Stored Beam & Injection |
|
Wednesday, April 17, 2013 |
|
|
0000-0200 |
Measure accumulation limit (continued). |
Sajaev |
Stored Beam & Injection |
0200-0700 |
Set up 3NLSS lattice. |
Sajaev |
Stored Beam & Injection |
0200-0700 |
Injector training (parallel, when compatible). |
Oziemkowski |
Limited Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |