Machine Studies

Schedule for Run01-4, 2013

February 19th 0800 - February 20th 0800



Time

Descriptions

Studiers

SR Status

 

Tuesday, February 19, 2013

 

 

0800-0810

Collect XBPM orbit data

OPS

Stored Beam & Injection

0810-0930

Gap Scans and update IDGapFF look-up tables

Schroeder

Stored Beam &Injection

0930-1000

Troubleshoot B:IK MPEOB

Puttkammer

Prior to Booster Access

0930-1030

Adjust 5015 AHU settings

Erwin

No Beam

0930 -1130

Drill fence holes at S28.

Stevens

No Beam

0930-1130

Test Linac interlocks

Pietryla

No Injection

1000-1130

Map Linac gun area

Hoyt/Forrestal/Pasky

Access Linac

1000-1230

Replace FL3 screens

Berg

Access Booster

1030-1130

Leak check S38

Horan

Access Zone F

1130 -1230

Reboot FPGA BPM IOCs

Pietryla

No Beam

1230-1300

Recover SR beam.

OPS

Stored Beam & Injection

1300-1700

ID6 steering optimization.

Emery

Stored Beam & Injection

1700-2100

Xbpm alignment.

Decker Hahne

Stored Beam & Injection

2100-2400

IEX study

Xiao

Stored Beam & Injection

 

Wednesday, February 20, 2013

 

 

0000-0100

IEX study (continued).

Xiao

Stored Beam & Injection

0100-0300

Test fast RM measurement.

Sajaev

Stored Beam & Injection

0300-0700

Set up hybrid mode.

Sajaev

Stored Beam & Injection

0700-0800

Prepare for User beam

OPS

Stored Beam & Injection