Machine Studies
Draft Schedule for Run01-5, 2013
February 25 th 0800 – February 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Monday, February 25, 2012 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
Reboot interleaving DSPs |
PS group |
No Injection |
0930-1000 |
RF waveguide switch from RF3 to RF2 |
RF Group |
No Beam |
0930-1030 |
Investigate Power Fail light on iocs25bpm |
Laird |
No Beam |
0930-1130 |
Install new 352Mhz source |
DiMonte/Yao |
No Beam |
0930-1130 |
Temp. measurements at S25 |
Fors |
No Beam |
0930-1130 |
Archive CMPSI data at S39 |
Fors |
No Beam |
0930-1300 |
Test IEX global ID commands |
Smith |
Stored beam (may cause BPLD trip) |
0930-1330 |
RF5 cathode troubleshooting |
RF Group |
Limited Injection |
1000-1100 |
Map Linac PC gun area |
Pasky, et al |
Access Linac |
1030-1130 |
Replace fan tray in iocs17fb |
Laird |
No Beam |
1300-1600 |
Test rtfb IOC upgrade |
Xu |
Stored Beam & Injection |
1300-1500 |
Linac training (07-15). Parallel to IOC upgrade. |
Oziemkowski/Obasohan |
Limited Injection |
1600-1900 |
Install new P0 feedback clock. |
Yao Scaminaci |
Stored Beam & Injection |
1900-2100 |
Optimize booster injection controllaw. |
Yao |
Limited injection |
2100-2200 |
Set up P0 feedback for hybrid. |
Yao |
Stored Beam & Injection |
2200-2400 |
Orbit switch. |
Xiao |
Stored Beam & Injection |
|
Tuesday, February 26, 2012 |
|
|
0000-0200 |
Orbit switch (continued). |
Xiao |
Stored Beam & Injection |
0200-0600 |
IEX study. |
Xiao |
Stored Beam & Injection |
0600-0900 |
Complete hybrid lattice setup. |
Sajaev |
Stored Beam & Injection |
0900-1300 |
Local impedance measurement using RM. |
Sajaev |
Stored Beam & Injection |
1300-1500 |
Linac training (07-15) |
Oziemkowski/Obasohan |
Limited injection |
1500-1900 |
Test SCU0 heating with non-standard fill patterns. |
Harkay Boon |
Stored Beam & Injection |
1900-2100 |
Test ADC delay scan script. |
Sereno |
Stored Beam & Injection |
2100-2300 |
Collect 12 second FPGA data. |
Sereno |
Stored Beam & Injection |
2300-2400 |
Sextupole offset measurement. |
Xiao |
Stored Beam & Injection |
|
Wednesday, February 27, 2012 |
|
|
0000-0300 |
Sextupole offset measurement (continued). |
Xiao |
Stored Beam & Injection |
0300-0630 |
Restore APS-U lattice and test SPX sextupole compensation. |
Sajaev |
Stored Beam & Injection |
0630-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |