Machine Studies
Schedule for Run01-9, 2013
March 26 th 0800 – March 27th 0800
Time |
Descriptions |
Studiers |
SR Status |
|
Tuesday, March 26, 2013 |
|
|
0800-0810 |
Collect XBPM orbit data |
OPS |
Stored Beam & Injection |
0810-0930 |
Gap Scans and update IDGapFF look-up tables |
Schroeder |
Stored Beam & Injection |
0930-1000 |
S14 water skid valve switch |
Erwin |
No Beam |
0930-1030 |
Test solid state modulator switch |
Pietryla/Cours |
Limited Injection |
0930-1130 |
Test PEM changes |
Schroeder |
No Beam |
0930-1130 |
Install modulator module at RF2 |
RF Group |
No Beam |
0930-1130 |
Upgrade S38-04 rack temperature |
Blake |
No Beam |
0930-1130 |
Tune S35/36 Water skid PID |
Putnam/Erwin |
No Beam |
0930-1130 |
SR AHU PID tuning |
FMS |
No Beam |
0930-1130 |
Troubleshoot S30B:H3 |
Puttkammer |
No Beam |
1130-1200 |
Restore SR operation. |
OPS |
Stored Beam & Injection |
1200-1230 |
Test PID loop tuning for water loops. |
Erwin |
Stored Beam & Injection |
1230-1500 |
Test P0 feedback firmware fix. |
Yao Dimonte |
Stored Beam & Injection |
1500-1900 |
Xbpm data collection. |
Decker Hahne |
Stored Beam & Injection |
1900-2300 |
Corrector step response measurement. |
Sereno |
Stored Beam & Injection |
2300-2400 |
Accumulation limit characterization. |
Sajaev |
Stored Beam & Injection |
|
Wednesday, March 27, 2013 |
|
|
0000-0300 |
Accumulation limit characterization (continued). |
Sajaev |
Stored Beam & Injection |
0300-0700 |
Continue setting up 3NLSS+... lattice. |
Sajaev |
Stored Beam & Injection |
0700-0800 |
Prepare for User beam |
OPS |
Stored Beam & Injection |